   Weekly progress as on 27-07-2012
    
Si No  Activity Description  Total Quantity Cumulative progress upto last week  Balance  work up to last week Cumulative delay in Qty up to last week Work  planned  during the week  Actual work done during the week  Cumulative delay in Qty up to this week Work  Planned for next week  No of days remaining for completion as per the weekly plan Remarks 
1 PILE Muthambi side 27 27 0 0 0 0 0 0   Completed
2 PILE Thamarassery side 33 33 0 0 0 0 0 0   Completed
3 PILE NH SIDE 33 33 0 0 0 0 0 0   Completed
4 PILE CAP Muthambi SIDE 9 9 0 0 0 0 0 0   Completed
5 PILE CAP Thamarassery SIDE 11 11 0 0 0 0 0 0   Completed
6 PILE CAP NH SIDE 10 10 0 0 0 0 0 0   Completed
7 PIER Muthambi  SIDE 9 9 0 0 0 0 0 0   Completed
8 PIER Thamarassery SIDE 11 11 0 0 0 0 0 0   Completed
9 PIER NH SIDE 10 10 0 0 0 0 0 0   Completed
10 PIER CAP Muthambi  SIDE 9 8 1 0 1 1 0 0   Completed
11 PIER CAP Thamarassery SIDE 11 10 1 0 1 0 1 1 5 Work in progress
12 PIER CAP NH SIDE 10 9 1 0 0 0 0 0    
13 RE/R WALL Muthambi side 100% 0 100% 0 0.00% 0.00% 0 0.00%    
14 RE/R WALL Thamarassery side SIDE 100% 45% 55% 0 10.00% 0.00% 0.1 10.00% 5 Raft& Side wall 2nd lift work in progress at one side.
15 RE/R WALL NH SIDE 100% 75% 65% 0 25.00% 0.00% 0.25 25.00% 5 Raft& Side wall 1st lift done .2nd lift work in progress
16 BEAM/SLAB Muthambi SIDE 8 5 3 0 2 2 0 1   shuttering work for deck between P10-AP2&P15-P16 in progress.Staging started for span P16-P17
17 BEAM/SLAB Thamarassery SIDE 10 9 1 0 0 0 0 0    
18 BEAM/SLAB NH SIDE 11 7 4 0 0 0 0 0 3 shuttering work between  P7-P8 for deck completed
19 HR/FP/KERB Muthambi SIDE 100% 50% 50% 0 25.00% 10.00% 0.15     Kerb casting&Hand rail fixing started
20 HR/FP/KERB thamarassery SIDE 100% 0 100% 0 0.00% 0.00% 0 10.00%    
21 HR/FP/KERB NH SIDE 100% 0 100% 0 25.00% 10.00% 0.15 25.00%   Kerb casting&Hand rail fixing started
22 BC/PAINTING 100% 0 100% 0 0.00% 0.00% 0 0.00%    
23 Utility shifting             0     KSEB utility shifting started. Shifted 1 post
                       
                       
                       
  Availbility of Men                     
  Date   21/7/2012 22/7/2012 23/7/2012 24/7/2012 25/7/2012 26/7/2012 27/7/2012    
  Nof labours   45 25 55 58 60 60 56    
                       
  Material Stocking Status Required Available Remarks              
  Coarse Aggreagate (m3) 60 90                
  Fine Aggreagate(m3) 60 90                
  Cement(bag) 1000 1100                
  Steel(MT) 40 75                
                       
                       
  Utility shifting                    
  Utilities to be shifted Status Remarks                
  BSNL                    
  KSEB                    
  KWA                    
  Others                    
 
Back
 
    
STAGING IN PROGRESS P16-P17

    
    
RW WORK NH SIDE

    
    
RETAINING WALL WORK NH SIDE

    
    
RETAINING WALL AP3 SIDE

    
 
    
LONG VIEW RAILWAY SPAN PORTION

    
    
GIRDER CONCRETE AP2-P10 SPAN

    
    
EXPANSION JOINT WORK IN PROGRESS

    
 
 
 

 

 

 

 

 

 

 