   Weekly Progress Report as on 20.07.2012
    
Sl.No Activity Description Total Quantity Cumulative Progress upto last week Balance work up to last week Cumulative delay in Qty up to last week Work planned during the week Actual work done during the week Cumulative delay in Qty up to this week Work planned for the next week
1 Piles 63 63 - - - - - -
2 Pile cap 21 21 - - - - - -
3 Pier  21 21 - - - - - -
4 PierCap 21 19 2 - 1 0 1 0
5 Deck Slab 21 9 12 - 0 0 0 Shuttering
7 Handrails 21 2 19 - 1 0 1 1
6 RC wall - Kuttipuram side 100% 25% 75% - 0% 0% 0% 0%
                   
                   
                   
Date 14.07.12 16.07.12 17.07.12 18.07.12 19.07.12 20.07.12      
Climate sunny Sunny sunny sunny sunny Sunny      
No. of labours 40 40 40 40 39 40      
                   
                   
Availability of Materials                
Material Required Available              
Fine aggregate 18 m3 22 m3              
Coarse Aggregate 22 m3 24 m3              
Cement 90bags 130 bags              
Steel 20 MT 25MT              
 
Back
 
    
BEAM SHUTTERING IN P12-P13

    
    
BEAM REINFORCEMENT IN P11-P12

      
 

 

 

 

 

 

 

 