KORATTY ROB
PROGRESS REPORT (upto July 20th 2012)
RAILWAY PORTION
Total scope: 4 Locations
LOCATIONS:P1,P7 ,P8,P2
P1,P7 –N.H side
P8,P2-Pulikkakadavu side.
Total Piles: 18
No of PILES IN EACH LOCATION
P1 location: 4
P7 location:5
P8 location:5
P2 location:4
WORK COMPLETED IN EACH LOCATION OF RAILWAY PORTION
P1 location:Piling completed (4 piles),pile cap,trestle column,trestle beam.
P7 location:5 pile concreting completed,pile cap,trestle column,trestle beam
P8 location:Piling completed(5 piles),pile cap,Trestle column,trestle beam
P2 location:Piling completed(4 piles),pile cap,trestle column,trestle beam.
Approach portion at N.H side completed 85%
WORK COMPLETED AT PULIKKAKADAVU SIDE
All deck slab concreting completed at pulikkakadavu side.
Works completed upto the roadworks,miscellaneous works, in the approach portion at pulikkakadavu side.
WORKS BALANCE
P1-P7 superstructure (RCC structure)
P7-P8 superstructure( CENTRAL SPAN)
P8-P2 superstructure (RCC structure)
Awaiting the sanction from the railways for the superstructure drawing.
WORK COMPLETED THIS WEEK
1 Fricion slab reinforcement and concreting work in progress at NH side.
2.Coping beam work completed
LABOUR REPORT
DATE
|
NO: OF LABOURS
|
14-07-2012
|
6
|
16-7-2012
|
5
|
17-7-2012
|
6
|
18-7-2012
|
6
|
19-7-2012
|
7
|
20-7-2012
|
6
|
|
|
|