   Weekly Progress Report as on 13.07.2012
    
Si No  Activity Description  Total Quantity Cumulative progress upto last week  Balance  work up to last week Cumulative delay in Qty up to last week Work  planned  during the week  Actual work done during the week  Cumulative delay in Qty up to this week Work  Planned for next week  No of days remaing for completion as per the weekly plan
1 Pile 48 48 0 0 0 0 0 0  
2 Pilecap 11 11 0 0 0 0 0 0  
3 Pier 9 9 0 0 0 0 0 0  
4 Piercap 9 9 0 0 0 0 0 0  
5 Abutment 2 2 0 0 0 0 0 0  
6 Abutment cap 2 1 1 1 1 0 1 1 6
7 Girders 30 15 15 15 1 0 15 1 6
8 Deckslab 10 5 5 3 0 0 4 0  
9 Handrails & footpath slab casting 100% 0.00% 100% 0% 0 0 0% 0  
10 Retaining Wall Edapalam side 100% 45.00% 55% 50% 22% 22% 45% 22% 6
11 Retaining Wall Moorkanad side 100% 0.00% 100% 0% 0 0 0% 0  
12 Road work Edapalam side 100% 0.00% 100% 0% 0 0 0% 0  
13 Road work Moorkanad side 100% 0.00% 100% 0% 0 0 0% 0  
            0        
  Availbility of Men                   
  Date 14/7/2012 15/7/2012 16/7/2012 17/7/2012 18/7/2012 19/7/2012 20/7/2012    
  No of labours 34 34 34 34 34 34 34    
                     
  Material Stocking Status                  
    Required Available Remarks            
  Coarse Aggreagate (m3) 95 cum 80 cum              
  Fine Aggreagate(m3) 50 cum 400 cum              
  Cement(bag) 600 bgs 435bgs              
  Steel(MT) 14  MT 60.59 MT              
 