Prevoius Weekly Reports

   weekly progress report as on 13/07/2012
    
Si No  Activity Description  Total Quantity Cumulative progress upto last week  Balance  work up to last week Cumulative delay in Qty up to last week Work  planned  during the week  Actual work done during the week  Cumulative delay in Qty up to this week Work  Planned for next week  No of days remaining for completion as per the weekly plan Remarks 
1 PILE Muthambi side 27 27 0 0 0 0 0 0   Completed
2 PILE Thamarassery side 33 33 0 0 0 0 0 0   Completed
3 PILE NH SIDE 33 33 0 0 0 0 0 0   Completed
4 PILE CAP Muthambi SIDE 9 9 0 0 0 0 0 0   Completed
5 PILE CAP Thamarassery SIDE 11 11 0 0 0 0 0 0   Completed
6 PILE CAP NH SIDE 10 10 0 0 0 0 0 0   Completed
7 PIER Muthambi  SIDE 9 9 0 0 0 0 0 0   Completed
8 PIER Thamarassery SIDE 11 10 1 0 1 0 1 1 5 1st lift done
9 PIER NH SIDE 10 10 0 0 0 0 0 0   Completed
10 PIER CAP Muthambi  SIDE 9 8 1 0 1 0 1 1 4  
11 PIER CAP Thamarassery SIDE 11 10 1 0 1 0 1 1    
12 PIER CAP NH SIDE 10 9 1 0 0 0 0 0    
13 RE/R WALL Muthambi side 100% 0 100% 0 0.00% 0.00% 0 0.00%    
14 RE/R WALL Thamarassery side SIDE 100% 40% 60% 0 10.00% 0.00% 0.1 10.00% 5 Raft& Side wall 1st lift done at one side.
15 RE/R WALL NH SIDE 100% 70% 65% 0 25.00% 0.00% 0.25 25.00% 5 Raft& Side wall 1st lift done .
16 BEAM/SLAB Muthambi SIDE 8 5 3 0 0 0 0 1   shuttering work for girder between P10-AP2 in progress.Staging done for span P15-P16
17 BEAM/SLAB Thamarassery SIDE 10 9 1 0 0 0 0 0 3  
18 BEAM/SLAB NH SIDE 11 7 4 0 0 0 0 0 3 shuttering work between  P7-P8 for deck completed
19 HR/FP/KERB Muthambi SIDE 100% 40% 60% 0 25.00% 5.00% 0.2 25.00%   Kerb casting&Hand rail fixing started
20 HR/FP/KERB thamarassery SIDE 100% 0 100% 0 0.00% 0.00% 0 0.00%    
21 HR/FP/KERB NH SIDE 100% 0 100% 0 25.00% 0.00% 0.25 25.00%    
22 BC/PAINTING 100% 0 100% 0 0.00% 0.00% 0 0.00%    
23 Utility shifting             0     KSEB utility shifting started. Shifted 1 post
                       
                       
                       
  Availbility of Men                     
  Date   7/7/2012 8/7/2012 9/7/2012 10/7/2012 11/7/2012 12/7/2012 13/7/2012    
  Nof labours   35 22 40 50 55 55 52    
                       
  Material Stocking Status Required Available Remarks              
  Coarse Aggreagate (m3) 60 75                
  Fine Aggreagate(m3) 60 75                
  Cement(bag) 1000 250                
  Steel(MT) 35 60                
                       
                       
  Utility shifting                    
  Utilities to be shifted Status Remarks                
  BSNL                    
  KSEB                    
  KWA                    
  Others                    
 
Back
 
    
STEEL WORK IN PROGRESS FOR AP2-P10

    
    
STAGING IN PROGRESS FOR P15-P16

    
    
SHUTTERING WORK IN PROGRESS FOR RETAINING WALL

    
    
P18 PIER 1ST LIFT

    
 
    
MR.NAGESH CONSULTANT ,RDS PROJECTS VISITED THE SITE FOR T JUNCTION DESIGN

    
    
KERB &HAND RAIL WORK IN PROGRESS AT AP2

    
    
CONCRETING IN PROGRESS FOR RW AP3 SIDE

    
 
 
 

 

 

 

 

 

 

 