Untitled Document
Road to Prosperity
Site last updated on:  12-12-2020 | You are visitor: 8054028
Completed Projects Projects Under Construction Citizen Services Careers Right to Service


Prevoius Weekly Reports

   Weekly progress report as on 13.07.2012
    
Sl No  Activity Description  Total Quantity Cumulative progress upto last week  Balance  work up to last week Cumulative delay in Qty up to last week Work  planned  during the week  Actual work done during the week  Cumulative delay in Qty up to this week Work  Planned for next week  No of days remaing for completion as per the weekly plan Remarks 
1 PILE CHERUVATHOOR  SIDE 27 27 Completed    
2 PILE PADANNA SIDE 24 24 Completed    
3 PILE CAP CHERUVATHOOR SIDE 9 9 Completed    
4 PILE CAP  PADANNA SIDE 8 8 Completed    
5 PIER CHERUVATHOOR SIDE 9 9 Completed    
6 PIER PADANNA SIDE 8 8 Completed    
7 PIER CAP CHERUVATHOOR SIDE 9 9 Completed    
8 PIER CAP PADANNA SIDE 8 8 Completed    
9 RE/RC WALL CHERUVATHOOR  SIDE 100% 80% 20% 20% 0.00% 0.00% 20.00% 0.00%   RE Panel works held up due to rain and unavailability of red earth
10 RE/RC  WALL PADANNA SIDE 100% 44% 56% 20% 3.00% 2.00% 1.00% 2.00%    
11 BEAM/SLAB CHERUVATHOOR  SIDE 9 6.5 2.5 1 0.5 0.5 0 0   P10-P9 Deck slab complete
12 BEAM/SLAB PADANNA SIDE 8 7 1 complete except railway adjacent span    
13 EXPANSION JOINT CHERUVATHUR SIDE 9 5 4 0 0 0 0 0    
14 EXPANSION JOINT PADANNA SIDE 8 1 7 3 3 2 1 2   P1,P3 locations complete
15 KERB CHERUVATHOOR  SIDE 100% 67.50% 33% 0 0.00% 0.00% 0.00% 0.00%   kerb complete for AP2-P10 spans
16 KERB PADANNA SIDE 100% 84% 16% 0 0.00% 0.00% 0.00% 0.00%    
17 HANDRAIL CHERUVATHUR SIDE 100% 45% 55% 0 0.00% 0.00% 0.00% 0.00%   complete for AP2-P10 spans
18 HANDRAIL PADANNA SIDE 100% 48% 52% 0% 24.00% 12.00% 12.00% 24.00%   P5-P6 span complete
17 BC/PAINTING 100% 0 100% 0 0.00% 0.00% 0.00% 0.00%    
18 Others                   Drainage works complete for 56 m at chr side.
19 Deck Slab                    
20 Utility shifting                    
                       
                       
                       
  Availbility of Men                     
  Date 07-07-2012 08-07-2012 09-07-2012 10-07-2012 11-07-2012 12-07-2012 13-07-2012      
  No of labours 58 18 58 51 50 51 57      
                       
  Material Stocking Status Required Available Remarks              
  Coarse Aggreagate (m3) available                
  Fine Aggreagate(m3) available                
  Cement(bag) 200 1000              
  Steel(MT) 6 15              
 
Back
 
    
RC WALL PADANNA SIDE (2)

    
    
P10-P9 DECK SLAB CONCRETE IP

    
    
P1 EXPANSION JOINT CONCRETE

    
    
HANDRAIL ERECTION IP AT P6-P7

    
 
 
 

 

 

 

 

 

 

 

Untitled Document