   Weekly Progress Report as on 06.07.2012
    
Sl.No Activity Description Total Quantity Cumulative Progress upto last week Balance work up to last week Cumulative delay in Qty up to last week Work planned during the week Actual work done during the week Cumulative delay in Qty up to this week Work planned for the next week
1 Piles 63 63 - - - - - -
2 Pile cap 21 21 - - - - - -
3 Pier  21 21 - - - - - -
4 PierCap 21 18 3 - 1 1 0 1
5 Deck Slab 21 8 13 - 1 1 0 staging works
7 Handrails 21 0 21 - 2 2 0 1
6 RC wall - Kuttipuram side 100% 25% 75% - 0% 0% 0% 0%
                   
                   
                   
Date 30.06.12 02.07.12 03.07.12 04.07.12 05.07.12 06.07.12      
Climate sunny Rain Rain Rain sunny Sunny      
No. of labours 48 33 30 30 30 25      
                   
                   
Availability of Materials                
Material Required Available              
Fine aggregate 15 m3 22 m3              
Coarse Aggregate 20 m3 30 m3              
Cement 100bags 150 bags              
Steel 20 MT 25MT              
 
Back
 
    
SLAB CONCRETING IN P13-P14

    
    
RCC WALL AT KUTTIPURAM SIDE

    
    
PIER CAP COMPLETED IN P11

    
    
HANDRAIL POST IN AP2-P19

    
 
 
 

 

 

 

 

 

 

 