Prevoius Weekly Reports

   Weekly progress as on 06-07-2012
    
Si No  Activity Description  Total Quantity Cumulative progress upto last week  Balance  work up to last week Cumulative delay in Qty up to last week Work  planned  during the week  Actual work done during the week  Cumulative delay in Qty up to this week Work  Planned for next week  No of days remaining for completion as per the weekly plan Remarks 
1 PILE Muthambi side 27 27 0 0 0 0 0 0   Completed
2 PILE Thamarassery side 33 33 0 0 0 0 0 0   Completed
3 PILE NH SIDE 33 33 0 0 0 0 0 0   Completed
4 PILE CAP Muthambi SIDE 9 9 0 0 0 0 0 0   Completed
5 PILE CAP Thamarassery SIDE 11 11 0 0 0 0 0 0   Completed
6 PILE CAP NH SIDE 10 10 0 0 0 0 0 0   Completed
7 PIER Muthambi  SIDE 9 9 0 0 0 0 0 0   Completed
8 PIER Thamarassery SIDE 11 10 1 0 1 0 1 1 5 Work in progress.
9 PIER NH SIDE 10 10 0 0 0 0 0 0   Completed
10 PIER CAP Muthambi  SIDE 9 8 1 0 1 0 1 1 5 steel work in progress
11 PIER CAP Thamarassery SIDE 11 10 1 0 0 0 0 1    
12 PIER CAP NH SIDE 10 9 1 0 0 0 0 0    
13 RE/R WALL Muthambi side 100% 0 100% 0 0.00% 0.00% 0 0.00%    
14 RE/R WALL Thamarassery side SIDE 100% 40% 60% 0 10.00% 0.00% 0.1 10.00% 5 Raft& Side wall 1st lift done at one side.
15 RE/R WALL NH SIDE 100% 65% 65% 0 25.00% 5.00% 0.2 25.00% 5 Raft& Side wall 1st lift done .
16 BEAM/SLAB Muthambi SIDE 8 5 3 0 0 0 0 1    
17 BEAM/SLAB Thamarassery SIDE 10 8 2 0 1 1 0 0 3 shuttering work for deck slab between P19-P20 in progress
18 BEAM/SLAB NH SIDE 11 7 4 0 0 0 0 0 3 shuttering work between  P7-P8 for deck completed
19 HR/FP/KERB Muthambi SIDE 100% 25% 75% 0 25.00% 15.00% 0.1 25.00%   Kerb casting&Hand rail fixing started
20 HR/FP/KERB thamarassery SIDE 100% 0 100% 0 0.00% 0.00% 0 0.00%    
21 HR/FP/KERB NH SIDE 100% 0 100% 0 0.00% 0.00% 0 25.00%    
22 BC/PAINTING 100% 0 100% 0 0.00% 0.00% 0 0.00%    
23 Utility shifting             0     KSEB utility shifting started. Shifted 1 post
                       
                       
                       
  Availbility of Men                     
  Date   30/6/2012 07-01-12 07-02-12 07-03-12 07-04-12 07-05-12 07-06-12    
  Nof labours   25 25 40 52 58 65 65    
                       
  Material Stocking Status Required Available Remarks              
  Coarse Aggreagate (m3) 60 75                
  Fine Aggreagate(m3) 60 75                
  Cement(bag) 1000 100                
  Steel(MT) 35 55                
                       
                       
  Utility shifting                    
  Utilities to be shifted Status Remarks                
  BSNL                    
  KSEB                    
  KWA                    
  Others                    
 
Back
 
    
WATERLOGGING IN AP3 SIDE

    
    
STAGING JUST STARTED AT P15-P16

    
    
STAGING JUST STARTED AT P15-P16

    
    
STAGING JUST STARTED AT P15-P16

    
 
    
STAGING IN PROGRESS AP2-P10

    
    
STAGING IN PROGRESS AP2-P10

    
    
MIXER MACHINE SETTING UNDER DECK SLAB

    
 
    
GIRDER CONCRETING P19-P20

    
    
FINISHING WORKS STARTED AT AP2 SIDE

    
    
FINISHING WORKS STARTED AT AP2 SIDE

    
 
 
 

 

 

 

 

 

 

 