weekly progress 6.7.2012 |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
Progress Report For Anayara ROB for the week ending on 6.7.2012 |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
Sl No |
Activity Description |
Total Quantity |
Cumulative progress upto 6.7.12 |
Balance work up to 6.7.12 |
Cumulative delay in Qty up to 6.7.12 |
Work planned during the week |
Actual work done during the week |
Delay in Qty up to this week |
Work Planned for next week |
1 |
PILE Pettah side(Approach portion) |
12 |
12 |
0 |
0 |
0 |
0 |
0 |
0 |
2 |
PILE Anayara side(Approach portion) |
12 |
12 |
0 |
0 |
0 |
0 |
0 |
0 |
3 |
PILE CAP Pettah side(Approach portion) |
4 |
4 |
0 |
0 |
0 |
0 |
0 |
0 |
4 |
PILE CAP Anayara side(Approach portion) |
4 |
4 |
0 |
0 |
0 |
0 |
0 |
0 |
5 |
PIER Pettah side(Approach portion) |
4 |
4 |
0 |
0 |
0 |
0 |
0 |
0 |
6 |
PIER Anayara side(Approach portion) |
4 |
4 |
0 |
0 |
0 |
0 |
0 |
0 |
7 |
PIER CAP Pettah side(Approach portion) |
4 |
4 |
0 |
0 |
0 |
0 |
0 |
0 |
|
PIER CAP Anayara side(Approach portion) |
4 |
4 |
0 |
0 |
0 |
0 |
0 |
0 |
8 |
GIRDER Pettah side(Approach portion) |
4 |
1 |
3 |
|
|
|
|
|
9 |
GIRDER Anayara side(Approach portion) |
4 |
2.5 |
1.5 |
|
|
0.5 |
|
|
10 |
Service Road Pettah side(Approach portion) |
1400 |
350 |
1050 |
|
|
|
|
|
11 |
Service Road Anayara side(Approach portion) |
1400 |
350 |
1050 |
|
|
|
|
|
12 |
RT Wall Pettah side(Approach portion) % |
100 |
88 |
12 |
|
|
|
|
|
13 |
RT Wall Anayara side(Approach portion) % |
100 |
88 |
12 |
|
|
|
|
|
14 |
RE Wall Panel Casting Pettah side(Approach portion) |
400 |
400 |
0 |
|
|
|
|
|
15 |
RE Wall Panel Casting Anayara side(Approach portion) |
400 |
370 |
30 |
|
|
|
|
|
16 |
RE Wall Panel Erection Pettah side(Approach portion) |
400 |
296 |
104 |
|
|
|
|
|
17 |
RE Wall Panel Erection Anayara side(Approach portion) |
400 |
315 |
85 |
|
|
|
|
|