Untitled Document
Road to Prosperity
Site last updated on:  12-12-2020 | You are visitor: 7887049
Completed Projects Projects Under Construction Citizen Services Careers Right to Service


Prevoius Weekly Reports

   weekly progress report as on 06/07/2012
    
weekly progress 6.7.2012                
                   
Progress Report For Anayara ROB for the week ending on 6.7.2012        
                   
Sl No  Activity Description  Total Quantity Cumulative progress upto 6.7.12 Balance  work up to 6.7.12 Cumulative delay in Qty up to 6.7.12 Work  planned  during the week  Actual work done during the week  Delay in Qty up to this week Work  Planned for next week 
1 PILE  Pettah side(Approach portion) 12 12 0 0 0 0 0 0
2 PILE Anayara side(Approach portion) 12 12 0 0 0 0 0 0
3 PILE CAP Pettah side(Approach portion) 4 4 0 0 0 0 0 0
4 PILE CAP Anayara side(Approach portion) 4 4 0 0 0 0 0 0
5 PIER Pettah side(Approach portion) 4 4 0 0 0 0 0 0
6 PIER Anayara side(Approach portion) 4 4 0 0 0 0 0 0
7 PIER  CAP Pettah side(Approach portion) 4 4 0 0 0 0 0 0
  PIER  CAP Anayara side(Approach portion) 4 4 0 0 0 0 0 0
8 GIRDER Pettah side(Approach portion) 4 1 3          
9 GIRDER Anayara side(Approach portion) 4 2.5 1.5     0.5    
10 Service Road Pettah side(Approach portion) 1400 350 1050          
11 Service Road Anayara side(Approach portion) 1400 350 1050          
12 RT Wall Pettah side(Approach portion) % 100 88 12          
13 RT Wall Anayara side(Approach portion) % 100 88 12                
14 RE Wall Panel Casting Pettah side(Approach portion) 400 400 0          
15 RE Wall Panel Casting Anayara side(Approach portion) 400 370 30          
16 RE Wall Panel Erection Pettah side(Approach portion) 400 296 104          
17 RE Wall Panel Erection Anayara side(Approach portion) 400 315 85          
 
Back
 
    
HANDRAIL

    
    
GIRDER P2-P3 CONCRETE

      
 

 

 

 

 

 

 

 

Untitled Document