Prevoius Weekly Reports

   weekly progress report as on 06/07/2012
    
  Description Completed/ Progress Remarks
IV ROB at Parappanangady    
  Pier cap (Total no of pier Cap- 21) Completed 21 NOS COMPLETED
  RE Wall panel casting ( total600 nos) Completed Errection completed.
  Slab calicut side  (total 10 nos ) In progress 9nos done  (adjacent span pending )
  slab NH side ( 11 nos) In progress 10nos done  (adjacent span pending )
  Retaining wall NH side completed completed
  Retaining wall calicut side completed  completed
  Dirt wall AP2 concreting  completed Done 100%
  Dirt wall AP1 concreting  completed Done 100%
  Handrail casting completed 1400 nos completed.
  Handrail fixing completed  completed.
  RAILWAY PORTION    
  Pilling work  Completed PILING COMPLETED
   RP1 In progress pier ,piercap completed
   RP2 In progress pier completed,piercap work started.
   RP3 In progress Pier completed
   RP4 In progress pier completed,piercap COMPLETED.
  NH side RE panel erection completed 100% completed.
  RE wall work calicut side. completed 100% completed.
  expansion joint  completed completed.
  painting-slab In progress Existing structures completed.
 
Back
 
    
RP4 PIERCAP CONCRETING.

    
    
RP3 PIER COMPLETED.

    
    
RAILWAY PORTION IN PROGRESS.

    
    
PIERCAP STAGING IN RP2.

    
 
 
 

 

 

 

 

 

 

 