Untitled Document
Road to Prosperity
Site last updated on:  12-12-2020 | You are visitor: 7888555
Completed Projects Projects Under Construction Citizen Services Careers Right to Service


Prevoius Weekly Reports

   Weekly progress Report as on 06.07.2012
    
Si No  Activity Description  Total Quantity Cumulative progress upto last week  Balance  work up to last week Cumulative delay in Qty up to last week Work  planned  during the week  Actual work done during the week  Cumulative delay in Qty up to this week Work  Planned for next week  No of days remaing for completion as per the weekly plan Remarks 
1 PILE  CALICUT  SIDE 48 48 0 1 0 0 1 0    
2 PILE THIRUR SIDE 24 24 0 11 0 0 11 0    
3 PILE CAP CALICUT  SIDE 12 12 0 1 0 0 1 0    
4 PILE CAP  THIRURSIDE 6 6 0 5 0 0 5 0    
5 PIER CALICUT SIDE 12 12 0 1 0 0 1 0    
6 PIER THIRUR SIDE 6 6 0 1 0 0 1 0    
7 PIER CAPCALICUT   SIDE 12 12 0 2 0 0 2 0    
8 PIER CAP THIRUR SIDE 6 6 0 3 0 0 3 0    
9 RETAINING WALL WALL CALICUT   SIDE 100% 65.00% 35% 0 0.00% 0.00% 30.00% 0.00%    
10 RETAINING WALL THIRUR SIDE 100% 25% 75% 0 10.00% 5.00% 35.00% 10.00%    
11 BEAM CALICUT   SIDE 12 6 6 0 0 0 4 0    
12 SLAB CALICUT SIDE 12 5 7   1 1 7 0    
13 BEAM THIRUR SIDE 6 3 3 0 1 0 7 1    
14 SLAB TIRUR SIDE 6 1 6   0 0 1 1    
15 HR/FP/KERB CALICUT   SIDE 100% 0 100% 0 0.00% 0.00% 5.00% 0.00%    
16 HR/FP/KERBTHIRUR SIDE 100% 0 100% 0 0.00% 0.00% 0.00% 0.00%    
17 BC/PAINTING 100% 0 100% 0 0.00% 0.00% 0.00% 0.00%    
18 Deck Slab                    
17 Utility shifting                    
                       
                       
                       
  Availbility of Men                   
  Date 30-06-2012 01-07-2012 02-07-2012 03-07-2012 04-07-2012 05-07-2012 06-07-2012      
  Nof labours 57 57 57 57 57 57 57      
                       
  Material Stocking Status Required Available Remarks              
  Coarse Aggreagate (m3)       RMC            
  Fine Aggreagate(m3)                    
  Cement(bag)                    
  Steel(MT)                    
                       
                       
  Utility shifting                    
  Utilities to be shifted Status Remarks                
  BSNL shifting completed                  
  KSEB shifting in progress                  
  KWA shifting completed                  
  Others                    
 
Back
 
    
P10-P11 GIRDER STAGING

    
    
RETAINING WALL TIRUR SIDE

    
    
PROFILING P13-P14

    
    
P13-P14 GIRDER SHUTTERING

    
 
 
 

 

 

 

 

 

 

 

Untitled Document