Progress Report For ROB Puliyanam for the week ending on 06.07.2012 |
Sl No |
Activity Description |
Total Quantity |
Cumulative progress upto last week |
Balance work up to last week |
Cumulative delay in Qty up to last week |
Work planned during the week |
Actual work done during the week |
Cumulative delay in Qty up to this week |
Work Planned for next week |
Remarks |
1 |
Pile towards NH side |
26 |
26 |
0 |
0 |
0 |
0 |
0 |
0 |
TARGET ACHIEVED |
2 |
Pile towards Puliyanam side |
18 |
18 |
0 |
0 |
0 |
0 |
0 |
0 |
TARGET ACHIEVED |
3 |
Pile cap at NH Side |
6 |
6 |
0 |
0 |
0 |
0 |
0 |
0 |
TARGET ACHIEVED |
4 |
Pile Cap at Puliyanamside |
4 |
4 |
0 |
0 |
0 |
0 |
0 |
0 |
TARGET ACHIEVED |
5 |
RC wall at Puliyanam side |
100% |
100% |
0 |
0 |
0 |
0 |
0 |
0 |
TARGET ACHIEVED |
6 |
RC wall at NH side |
100% |
100% |
0 |
0 |
0 |
0 |
0 |
0 |
TARGET ACHIEVED |
7 |
Pier at NH Side |
6 |
6 |
0 |
0 |
0 |
0 |
0 |
0 |
TARGET ACHIEVED |
8 |
Pier at Puliyanam Side |
4 |
4 |
0 |
0 |
0 |
0 |
0 |
0 |
TARGET ACHIEVED |
9 |
Piercap at NH Side |
6 |
6 |
0 |
0 |
0 |
0 |
0 |
0 |
TARGET ACHIEVED |
10 |
Piercap at Puliyanam |
4 |
4 |
0 |
0 |
0 |
0 |
0 |
0 |
TARGET ACHIEVED |
11 |
PEDESTAL |
54 |
54 |
0 |
0 |
0 |
0 |
0 |
0 |
TARGET ACHIEVED |
12 |
Beam and cross beam at NH side |
6 |
5 |
1 |
0 |
0 |
0 |
0 |
0 |
TARGET ACHIEVED (EXCLUDING RAILWAY ADJACENT SPAN) |
13 |
Beam and cross beam at Puliyanam side |
4 |
3 |
1 |
0 |
0 |
0 |
0 |
0 |
TARGET ACHIEVED (EXCLUDING RAILWAY ADJACENT SPAN) |
14 |
Deck slab at NH side |
6 |
5 |
1 |
0 |
0 |
0 |
0 |
0 |
TARGET ACHIEVED (EXCLUDING RAILWAY ADJACENT SPAN) |
15 |
Deck slab at Puliyanam side |
4 |
3 |
1 |
0 |
0 |
0 |
0 |
0 |
TARGET ACHIEVED (EXCLUDING RAILWAY ADJACENT SPAN) |
16 |
Dirt wall |
2 |
2 |
0 |
0 |
0 |
0 |
0 |
0 |
TARGET ACHIEVED (EXCLUDING RAILWAY ADJACENT SPAN) |
17 |
Kerb NH side |
100% |
90% |
10% |
0 |
0% |
0% |
0% |
0% |
TARGET ACHIEVED (EXCLUDING RAILWAY ADJACENT SPAN) |
18 |
Kerb Puliyanam side |
100% |
85% |
15% |
0 |
0% |
0% |
0% |
0% |
TARGET ACHIEVED (EXCLUDING RAILWAY ADJACENT SPAN) |
19 |
Earth filling in approach embankment |
100% |
100% |
0% |
0 |
0% |
0% |
0% |
0% |
TARGET ACHIEVED |
20 |
Hand rail fixing -Puliyanam side |
100% |
100% |
0 |
0 |
0 |
0 |
0 |
0 |
TARGET ACHIEVED |
21 |
Hand rail fixing -NH side |
100% |
100% |
0% |
0% |
20% |
20% |
0% |
0% |
TARGET ACHIEVED |
22 |
Expansion Joints |
7 |
5 |
2 |
0 |
4 |
4 |
0 |
0 |
TARGET ACHIEVED (EXCLUDING RAILWAY ADJACENT SPAN) |
23 |
WBM |
100% |
67% |
33% |
0 |
67% |
33% |
0% |
33% |
|
|
|
|
|
|
|
|
|
|
|
|
Date |
30.6.12 |
2.7.12 |
3.7.12 |
4.7.12 |
5.7.12 |
6.7.12 |
|
|
|
|
Climate |
rainy |
rainy |
rainy |
rainy |
rainy |
rainy |
|
|
|
|
No.of labours |
22 |
23 |
22 |
22 |
22 |
22 |
|
|
|
|