   Weekly progress report as on 29.06.2012
    
Si No  Activity Description  Total Quantity Cumulative progress upto last week  Balance  work up to last week Cumulative delay in Qty up to last week Work  planned  during the week  Actual work done during the week  Cumulative delay in Qty up to this week Work  Planned for next week  No of days remaining for completion as per the weekly plan Remarks 
1 PILE Muthambi side 27 27 0 0 0 0 0 0   Completed
2 PILE Thamarassery side 33 33 0 0 0 0 0 0   Completed
3 PILE NH SIDE 33 33 0 0 0 0 0 0   Completed
4 PILE CAP Muthambi SIDE 9 9 0 0 0 0 0 0   Completed
5 PILE CAP Thamarassery SIDE 11 10 1 0 1 1 0 0   Completed
6 PILE CAP NH SIDE 10 10 0 0 0 0 0 0   Completed
7 PIER Muthambi  SIDE 9 9 0 0 0 0 0 0   Completed
8 PIER Thamarassery SIDE 11 10 1 0 1 0 1 1 5 Work in progress.
9 PIER NH SIDE 10 9 1 0 1 1 0 0   Completed
10 PIER CAP Muthambi  SIDE 9 6 3 0 3 2 1 1 5 steel work in progress
11 PIER CAP Thamarassery SIDE 11 10 1 0 0 0 0 1    
12 PIER CAP NH SIDE 10 9 1 0 0 0 0 0    
13 RE/R WALL Muthambi side 100% 0 100% 0 0.00% 0.00% 0 0.00%    
14 RE/R WALL Thamarassery side SIDE 100% 35% 65% 0 10.00% 5.00% 0.05 10.00% 5 Raft& Side wall 1st lift done at one side.
15 RE/R WALL NH SIDE 100% 55% 65% 0 25.00% 10.00% 0.15 25.00% 5 Raft& Side wall 1st lift done .
16 BEAM/SLAB Muthambi SIDE 8 5 3 0 0 0 0 0    
17 BEAM/SLAB Thamarassery SIDE 10 7 3 0 2 1 1 1 3 shuttering work between P19-P20 completed concreting on 01.07.12
18 BEAM/SLAB NH SIDE 11 7 4 0 0 0 0 0 3 shuttering work between  P7-P8 for deck completed
19 HR/FP/KERB Muthambi SIDE 100% 10% 90% 0 15.00% 15.00% 0 25.00%   Kerb casting&Hand rail fixing started
20 HR/FP/KERB thamarassery SIDE 100% 0 100% 0 0.00% 0.00% 0 0.00%    
21 HR/FP/KERB NH SIDE 100% 0 100% 0 0.00% 0.00% 0 0.00%    
22 BC/PAINTING 100% 0 100% 0 0.00% 0.00% 0 0.00%    
23 Utility shifting             0     KSEB utility shifting started. Shifted 1 post
                       
                       
                       
  Availbility of Men                     
  Date   23/6/2012 24/6/2012 25/6/2012 26/6/2012 27/6/2012 28/6/2012 29/6/2012    
  Nof labours   70 25 40 40 48 47 52    
                       
  Material Stocking Status Required Available Remarks              
  Coarse Aggreagate (m3) 50 70                
  Fine Aggreagate(m3) 50 70                
  Cement(bag) 1000 50                
  Steel(MT) 40 55                
                       
                       
  Utility shifting                    
  Utilities to be shifted Status Remarks                
  BSNL                    
  KSEB                    
  KWA                    
  Others                    
 
Back
 
    
RETAINING WALL WORK IN PROGRESS AT AP1

    
    
PIER P9A FINAL LIFT

    
    
PIER CAP P16

    
    
LONG VIEW FROM MUTHAMBI SIDE

    
 
 
 

 

 

 

 

 

 

 