Prevoius Weekly Reports
|
28.08.2010 |
| |
ROB at Mulamkunnathukavu
|
Work Planned upto 28/8/2010 |
Completed / Progress |
Remarks |
|
SubStructure & Foundation Drg |
Submitted |
Pile capacity calculation not submitted |
|
Super Structure Drg |
Not Submitted |
|
|
Trial Boring and soil Investigation |
completed |
|
|
Construction activities |
Not Started |
|
|
| |
| Back |
| |
No images are uploaded for this Weekly Reports
|
| |
|