Prevoius Weekly Reports
|
28.08.2010 |
|
ROB at Mulamkunnathukavu
Work Planned upto 28/8/2010 |
Completed / Progress |
Remarks |
SubStructure & Foundation Drg |
Submitted |
Pile capacity calculation not submitted |
Super Structure Drg |
Not Submitted |
|
Trial Boring and soil Investigation |
completed |
|
Construction activities |
Not Started |
|
|
|
Back |
|