Untitled Document
Road to Prosperity
Site last updated on:  12-12-2020 | You are visitor: 7887028
Completed Projects Projects Under Construction Citizen Services Careers Right to Service


Prevoius Weekly Reports

   Weekly Progress Report as on 29/06/2012
    
Sl No   Activity Description   Total Quantity  Cumulative progress upto last week   Balance  work up to last week  Cumulative delay in Qty up to last week  Work  planned  during the week   Actual work done during the week   Cumulative delay in Qty up to this week  Work  Planned for next week   Remarks 
1 Pile towards NH side 26 26 0 0 0 0 0 0 TARGET ACHIEVED
2 Pile towards Puliyanam side 18 18 0 0 0 0 0 0 TARGET ACHIEVED
3 Pile cap at NH  Side 6 6 0 0 0 0 0 0 TARGET ACHIEVED
4 Pile Cap at Puliyanamside 4 4 0 0 0 0 0 0 TARGET ACHIEVED
5 RC wall at Puliyanam side 100% 100% 0 0 0 0 0 0 TARGET ACHIEVED
6 RC wall at NH side 100% 100% 0 0 0 0 0 0 TARGET ACHIEVED
7 Pier at NH Side 6 6 0 0 0 0 0 0 TARGET ACHIEVED
8 Pier at Puliyanam Side 4 4 0 0 0 0 0 0 TARGET ACHIEVED
9 Piercap at NH Side 6 6 0 0 0 0 0 0 TARGET ACHIEVED
10 Piercap at Puliyanam 4 4 0 0 0 0 0 0 TARGET ACHIEVED
11 PEDESTAL 54 54 0 0 0 0 0 0 TARGET ACHIEVED
12 Beam and cross beam at NH side 6 5 1 0 0 0 0 0 TARGET ACHIEVED (EXCLUDING RAILWAY ADJACENT SPAN) 
13 Beam and cross beam at Puliyanam side  4 3 1 0 0 0 0 0 TARGET ACHIEVED (EXCLUDING RAILWAY ADJACENT SPAN) 
14 Deck slab  at NH side  6 5 1 0 0 0 0 0 TARGET ACHIEVED (EXCLUDING RAILWAY ADJACENT SPAN) 
15 Deck slab  at Puliyanam side  4 3 1 0 0 0 0 0 TARGET ACHIEVED (EXCLUDING RAILWAY ADJACENT SPAN) 
16 Dirt wall  2 2 0 0 0 0 0 0 TARGET ACHIEVED (EXCLUDING RAILWAY ADJACENT SPAN) 
17 Kerb NH side 100% 90% 10% 0 0% 0% 0% 0% TARGET ACHIEVED (EXCLUDING RAILWAY ADJACENT SPAN) 
18 Kerb Puliyanam side 100% 85% 15% 0 0% 0% 0% 0% TARGET ACHIEVED (EXCLUDING RAILWAY ADJACENT SPAN) 
19 Earth filling in approach embankment  100% 100% 0% 0 0% 0% 0% 0% TARGET ACHIEVED
20 Hand rail fixing -Puliyanam side 100% 100% 0 0 0 0 0 0 TARGET ACHIEVED
21 Hand rail fixing -NH side 100% 80% 20% 0% 20% 15% 0% 20%  
22 Expansion Joints 7 1 6 0 0 0 1 1  
23 WBM  100% 33% 67% 0 0% 33% 0% 67%  
                     
Date 23.6.12 25.6.12 26.6.12 27.6.12 28.6.12 29.6.12        
Climate rainy rainy rainy rainy rainy rainy        
No.of labours 28 31 20 21 22 21        
                     
availability of material                    
materials Required Available                
Fine aggregate(M3) 5 10                
Coarse aggregate(M3) 6 10                
Cement(BAG) 100 200                
Steel(TONN) _ 28                
 
Back
 
    
WBM ON PULIYANAM SIDE RC WALL

    
    
WBM ON NH SIDE RC WALL

    
    
EXPANSION JOINT P10 LOCATION

    
    
HAND RAIL FXING , NH SIDE -26.06.2012

    
 
 
 

 

 

 

 

 

 

 

Untitled Document