Prevoius Weekly Reports

   Weekly Progress Report as on 29.06.2012
    
Sl.No Activity Description Total Quantity Cumulative Progress upto last week Balance work up to last week Cumulative delay in Qty up to last week Work planned during the week Actual work done during the week Cumulative delay in Qty up to this week Work planned for the next week
1 Piles 63 63 - - - - - -
2 Pile cap 21 21 - - - - - -
3 Pier  21 21 - - - - - -
4 PierCap 21 18 3 - 1 0 1 1
5 Deck Slab 21 7 14 - 1 1 0 1
6 RC wall - Kuttipuram side 100% 25% 75% - 3% 5% 3% 0%
                   
Date 23.06.12 25.06.12 26.06.12 27.06.12 28.06.12 29.06.12      
Climate Rain Rain Rain Rain Rain Sunny      
No. of labours 48 50 47 50 48 50      
                   
                   
Availability of Materials                
Material Required Available              
Fine aggregate 18 m3 20m3              
Coarse Aggregate 22 m3 30 m3              
Cement 100bags 190 bags              
Steel 24MT 28MT              
 
Back
 
    
SLAB SHUTTERING IN P14-P13

    
    
SLAB REINFORCEMENT COMPLETED IN P13-P14

    
    
PIER CAP P11 & P12

    
    
HAND RAIL POST SETTING IN KANJIPURA SIDE AP2-P19

    
 
 
 

 

 

 

 

 

 

 