   Weekly progress report as on 29.06.2012
    
Sl No  Activity Description  Total Quantity Cumulative progress upto last week  Balance  work up to last week Cumulative delay in Qty up to last week Work  planned  during the week  Actual work done during the week  Cumulative delay in Qty up to this week Work  Planned for next week  No of days remaing for completion as per the weekly plan Remarks 
1 PILE CHERUVATHOOR  SIDE 27 27 Completed    
2 PILE PADANNA SIDE 24 24 Completed    
3 PILE CAP CHERUVATHOOR SIDE 9 9 Completed    
4 PILE CAP  PADANNA SIDE 8 8 Completed    
5 PIER CHERUVATHOOR SIDE 9 9 Completed    
6 PIER PADANNA SIDE 8 8 Completed    
7 PIER CAP CHERUVATHOOR SIDE 9 9 Completed    
8 PIER CAP PADANNA SIDE 8 8 Completed    
9 RE/RC WALL CHERUVATHOOR  SIDE 100% 80% 20% 20% 0.00% 0.00% 20.00% 0.00%   RE Panel works held up due to rain and unavailability of red earth
10 RE/RC  WALL PADANNA SIDE 100% 40% 60% 10% 5.00% 2.00% 3.00% 3.00%   RC Wall first lift complete at both sides, 2nd lift complete for 15m at RHS.
11 BEAM/SLAB CHERUVATHOOR  SIDE 9 6 3 1 1 0 1 1   Shuttering  in progress for P10-P9 Girder,shortage of cement.
12 BEAM/SLAB PADANNA SIDE 8 7 1 complete except railway adjacent span    
13 EXPANSION JOINT CHERUVATHUR SIDE 9 5 4 0 0 0 0 0    
14 EXPANSION JOINT PADANNA SIDE 8 1 7 2 3 0 3 3   complaint for generator.
15 KERB CHERUVATHOOR  SIDE 100% 67.50% 33% 0 0.00% 0.00% 0.00% 0.00%   kerb complete for AP2-P10 spans
16 KERB PADANNA SIDE 100% 36% 64% 0 24.00% 24.00% 0.00% 24.00%   2 spans complete this week(P3-P4,P4-P5)
17 HANDRAIL CHERUVATHUR SIDE 100% 45% 55% 0 0.00% 0.00% 0.00% 0.00%   complete for AP2-P10 spans
18 HANDRAIL PADANNA SIDE 100% 0 100% 0 36.00% 12.00% 24.00% 24.00%   Handrail erection complete for RHS of P1-P2,P2-P3 spans,2 spans planned for next week.
17 BC/PAINTING 100% 0 100% 0 0.00% 0.00% 0.00% 0.00%    
18 Others                   Drainage works complete for 56 m at chr side.
19 Deck Slab                    
20 Utility shifting                    
                       
                       
                       
  Availbility of Men                     
  Date 23-06-2012 24-06-2012 25-06-2012 26-06-2012 27-06-2012 28-06-2012 29-06-2012      
  No of labours 57 33 57 57 57 32 57      
                       
  Material Stocking Status Required Available Remarks              
  Coarse Aggreagate (m3) available                
  Fine Aggreagate(m3) available                
  Cement(bag) 600 100 shortage at site            
  Steel(MT) 15 25              
                       
                       
  Utility shifting                    
  Utilities to be shifted Status Remarks                
  BSNL  Obstruction at Padanna side RC wall area to be cleared.            
  KSEB in progress electric post infront of unity hospital need to be shifted urgently.            
  KWA currently can be managed at site                   
  Others                    
 
Back
 
    
SHUTTERING IP FOR P10-P9 SPAN

    
    
RC WALL PADANNA SIDE

    
    
KERB SHUTTERING IP FOR P5-P6 SPAN

    
    
HANDRAIL CONCRETE IP FOR RHS OF P1-P2,P2-P3 SPANS

    
 
 
 

 

 

 

 

 

 

 