Sl No |
Activity Description |
Total Quantity |
Cumulative progress upto last week |
Balance work up to last week |
Cumulative delay in Qty up to last week |
Work planned during the week |
Actual work done during the week |
Cumulative delay in Qty up to this week |
Work Planned for next week |
No of days remaing for completion as per the weekly plan |
Remarks |
1 |
PILE CHERUVATHOOR SIDE |
27 |
27 |
Completed |
|
|
2 |
PILE PADANNA SIDE |
24 |
24 |
Completed |
|
|
3 |
PILE CAP CHERUVATHOOR SIDE |
9 |
9 |
Completed |
|
|
4 |
PILE CAP PADANNA SIDE |
8 |
8 |
Completed |
|
|
5 |
PIER CHERUVATHOOR SIDE |
9 |
9 |
Completed |
|
|
6 |
PIER PADANNA SIDE |
8 |
8 |
Completed |
|
|
7 |
PIER CAP CHERUVATHOOR SIDE |
9 |
9 |
Completed |
|
|
8 |
PIER CAP PADANNA SIDE |
8 |
8 |
Completed |
|
|
9 |
RE/RC WALL CHERUVATHOOR SIDE |
100% |
80% |
20% |
20% |
0.00% |
0.00% |
20.00% |
0.00% |
|
RE Panel works held up due to rain and unavailability of red earth |
10 |
RE/RC WALL PADANNA SIDE |
100% |
40% |
60% |
10% |
5.00% |
2.00% |
3.00% |
3.00% |
|
RC Wall first lift complete at both sides, 2nd lift complete for 15m at RHS. |
11 |
BEAM/SLAB CHERUVATHOOR SIDE |
9 |
6 |
3 |
1 |
1 |
0 |
1 |
1 |
|
Shuttering in progress for P10-P9 Girder,shortage of cement. |
12 |
BEAM/SLAB PADANNA SIDE |
8 |
7 |
1 |
complete except railway adjacent span |
|
|
13 |
EXPANSION JOINT CHERUVATHUR SIDE |
9 |
5 |
4 |
0 |
0 |
0 |
0 |
0 |
|
|
14 |
EXPANSION JOINT PADANNA SIDE |
8 |
1 |
7 |
2 |
3 |
0 |
3 |
3 |
|
complaint for generator. |
15 |
KERB CHERUVATHOOR SIDE |
100% |
67.50% |
33% |
0 |
0.00% |
0.00% |
0.00% |
0.00% |
|
kerb complete for AP2-P10 spans |
16 |
KERB PADANNA SIDE |
100% |
36% |
64% |
0 |
24.00% |
24.00% |
0.00% |
24.00% |
|
2 spans complete this week(P3-P4,P4-P5) |
17 |
HANDRAIL CHERUVATHUR SIDE |
100% |
45% |
55% |
0 |
0.00% |
0.00% |
0.00% |
0.00% |
|
complete for AP2-P10 spans |
18 |
HANDRAIL PADANNA SIDE |
100% |
0 |
100% |
0 |
36.00% |
12.00% |
24.00% |
24.00% |
|
Handrail erection complete for RHS of P1-P2,P2-P3 spans,2 spans planned for next week. |
17 |
BC/PAINTING |
100% |
0 |
100% |
0 |
0.00% |
0.00% |
0.00% |
0.00% |
|
|
18 |
Others |
|
|
|
|
|
|
|
|
|
Drainage works complete for 56 m at chr side. |
19 |
Deck Slab |
|
|
|
|
|
|
|
|
|
|
20 |
Utility shifting |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
Availbility of Men |
|
|
|
|
|
|
|
|
|
|
|
Date |
23-06-2012 |
24-06-2012 |
25-06-2012 |
26-06-2012 |
27-06-2012 |
28-06-2012 |
29-06-2012 |
|
|
|
|
No of labours |
57 |
33 |
57 |
57 |
57 |
32 |
57 |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
Material Stocking Status |
Required |
Available |
Remarks |
|
|
|
|
|
|
|
|
Coarse Aggreagate (m3) |
available |
|
|
|
|
|
|
|
|
|
Fine Aggreagate(m3) |
available |
|
|
|
|
|
|
|
|
|
Cement(bag) |
600 |
100 |
shortage at site |
|
|
|
|
|
|
|
Steel(MT) |
15 |
25 |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
Utility shifting |
|
|
|
|
|
|
|
|
|
|
|
Utilities to be shifted |
Status |
Remarks |
|
|
|
|
|
|
|
|
|
BSNL |
Obstruction at Padanna side RC wall area to be cleared. |
|
|
|
|
|
|
|
KSEB |
in progress |
electric post infront of unity hospital need to be shifted urgently. |
|
|
|
|
|
|
|
KWA |
currently can be managed at site |
|
|
|
|
|
|
|
|
|
|
Others |
|
|
|
|
|
|
|
|
|
|