Prevoius Weekly Reports

   Weekly progress report as on 22.06.2012
    
Sl.No Activity Description Total Quantity Cumulative Progress upto last week Balance work up to last week Cumulative delay in Qty up to last week Work planned during the week Actual work done during the week Cumulative delay in Qty up to this week Work planned for the next week
1 Piles 63 63 - - - - - -
2 Pile cap 21 21 - - - - - -
3 Pier  21 21 - - - - - -
4 PierCap 21 17 4 - 1 1 0 1
5 Deck Slab 21 7 14 - 1 0 1 1
6 RC wall - Kuttipuram side 100% 25% 75% - 3% 5% 3% 0%
                   
Date 16.06.12 18.06.12 19.06.12 20.06.12 21.06.12 22.06.12      
Climate Rain Rain Rain Rain Rain Rain      
No. of labours 50 50 47 46 50 50      
                   
                   
Availability of Materials                
Material Required Available              
Fine aggregate 16 m3 20m3              
Coarse Aggregate 30 m3 33 m3              
Cement 100bags 310 bags              
Steel 20MT 25MT              
 
Back
 
    
PIER CAP REINFORCEMENT WORKS IN P8

    
    
SLAB REINFORCEMENT WORKS IN P14-P15

    
    
PIER CAP CONCRETING IN P8

    
    
BEAM REINFORCEMENT IN P13-P14

    
 
 
 

 

 

 

 

 

 

 