   Weekly progress report as on 22.06.2012
    
Sl No  Activity Description  Total Quantity Cumulative progress upto last week  Balance  work up to last week Cumulative delay in Qty up to last week Work  planned  during the week  Actual work done during the week  Cumulative delay in Qty up to this week Work  Planned for next week  No of days remaing for completion as per the weekly plan Remarks 
1 PILE CHERUVATHOOR  SIDE 27 27 Completed    
2 PILE PADANNA SIDE 24 24 Completed    
3 PILE CAP CHERUVATHOOR SIDE 9 9 Completed    
4 PILE CAP  PADANNA SIDE 8 8 Completed    
5 PIER CHERUVATHOOR SIDE 9 9 Completed    
6 PIER PADANNA SIDE 8 8 Completed    
7 PIER CAP CHERUVATHOOR SIDE 9 9 Completed    
8 PIER CAP PADANNA SIDE 8 8 Completed    
9 RE/RC WALL CHERUVATHOOR  SIDE 100% 80% 20% 20% 0.00% 0.00% 20.00% 0.00%   RE Panel works held up due to rain and unavailability of red earth
10 RE/RC  WALL PADANNA SIDE 100% 33% 67% 10% 10.00% 10.00% 5.00% 5.00%   RC Wall LHS-Raft complete and wall first lift complete .
11 BEAM/SLAB CHERUVATHOOR  SIDE 9 6 3 1 0.5 0 1 1   Shuttering  in progress for P10-P9 Girder.
12 BEAM/SLAB PADANNA SIDE 8 7 1 complete except railway adjacent span    
13 EXPANSION JOINT CHERUVATHUR SIDE 9 5 4 0 0 0 0 0    
14 EXPANSION JOINT PADANNA SIDE 8 0 8 0 3 1 2 3    
15 KERB CHERUVATHOOR  SIDE 100% 67.50% 33% 0 0.00% 0.00% 0.00% 0.00%   kerb complete for AP2-P10 spans
16 KERB PADANNA SIDE 100% 0 100% 0 36.00% 36.00% 0.00% 24.00%   3 spans completed(P1-P2,P2-P3,P3-P4)
17 HANDRAIL CHERUVATHUR SIDE 100% 45% 55% 0 0.00% 0.00% 0.00% 0.00%   complete for AP2-P10 spans
18 HANDRAIL PADANNA SIDE 100% 0 100% 0 12.00% 0.00% 12.00% 36.00%   3 spans planned.
17 BC/PAINTING 100% 0 100% 0 0.00% 0.00% 0.00% 0.00%    
18 Others                   Drainage works complete for 40m at chr side.
19 Deck Slab                    
20 Utility shifting                    
                       
                       
                       
  Availbility of Men                     
  Date 16-06-2012 17-06-2012 18-06-2012 19-06-2012 20-06-2012 21-06-2012 22-06-2012      
  No of labours 67 16 68 67 68 68 59      
                       
  Material Stocking Status Required Available Remarks              
  Coarse Aggreagate (m3) available                
  Fine Aggreagate(m3) available                
  Cement(bag) 600 10 shortage at site            
  Steel(MT) 14 25              
                       
                       
  Utility shifting                    
  Utilities to be shifted Status Remarks                
  BSNL  Obstruction at Padanna side RC wall area to be cleared.            
  KSEB in progress electric post infront of unity hospital need to be shifted urgently.            
  KWA currently can be managed at site                   
  Others                    
 
Back
 
    
RC WALL FIRST LIFT CONCRETE

    
    
P2 LOCATION EXPANSION JOINT

    
    
KERB CONCRETE

    
    
CHR SIDE P8 LOCATION

    
 
    
CHR SIDE APPROACH AFFECTED BY RAIN

      
 

 

 

 

 

 

 

 