Untitled Document
Road to Prosperity
Site last updated on:  12-12-2020 | You are visitor: 7886961
Completed Projects Projects Under Construction Citizen Services Careers Right to Service


Prevoius Weekly Reports

   weekly progress report as on 29/06/2012
    
                   
Progress Report For Anayara ROB for the week ending on 22.6.2012      
                   
Sl No  Activity Description  Total Quantity Cumulative progress upto 22.6.12 Balance  work up to 22.6.12 Cumulative delay in Qty up to 22.6.12 Work  planned  during the week  Actual work done during the week  Delay in Qty up to this week Work  Planned for next week 
1 PILE  Pettah side(Approach portion) 12 12 0 0 0 0 0 0
2 PILE Anayara side(Approach portion) 12 12 0 0 0 0 0 0
3 PILE CAP Pettah side(Approach portion) 4 4 0 0 0 0 0 0
4 PILE CAP Anayara side(Approach portion) 4 4 0 0 0 0 0 0
5 PIER Pettah side(Approach portion) 4 4 0 0 0 0 0 0
6 PIER Anayara side(Approach portion) 4 4 0 0 0 0 0 0
7 PIER  CAP Pettah side(Approach portion) 4 4 0 0 0 0 0 0
  PIER  CAP Anayara side(Approach portion) 4 4 0 0 0 0 0 0
8 GIRDER Pettah side(Approach portion) 4 1 3          
9 GIRDER Anayara side(Approach portion) 4 2 2          
10 Service Road Pettah side(Approach portion) 1400 350 1050          
11 Service Road Anayara side(Approach portion) 1400 350 1050          
12 RT Wall Pettah side(Approach portion) % 100 88 12          
13 RT Wall Anayara side(Approach portion) % 100 88 12                
14 RE Wall Panel Casting Pettah side(Approach portion) 400 400 0          
15 RE Wall Panel Casting Anayara side(Approach portion) 400 350 50          
16 RE Wall Panel Erection Pettah side(Approach portion) 400 224 176          
17 RE Wall Panel Erection Anayara side(Approach portion) 400 296 104          
 
Back
 
    
SLAB CONCRETING P5_P6

      
 

 

 

 

 

 

 

 

Untitled Document