   Weekly progree report as on 22-06-2012
    
Si No  Activity Description  Total Quantity Cumulative progress upto last week  Balance  work up to last week Cumulative delay in Qty up to last week Work  planned  during the week  Actual work done during the week  Cumulative delay in Qty up to this week Work  Planned for next week  No of days remaining for completion as per the weekly plan Remarks 
1 PILE Muthambi side 27 27 0 0 0 0 0 0   Completed
2 PILE Thamarassery side 33 33 0 0 0 0 0 0   Completed
3 PILE NH SIDE 33 33 0 0 0 0 0 0   Completed
4 PILE CAP Muthambi SIDE 9 9 0 0 0 0 0 0   Completed
5 PILE CAP Thamarassery SIDE 11 10 1 0 1 0 1 1 2 Steel Work in progress & concreting on 23.06.12
6 PILE CAP NH SIDE 10 10 0 0 0 0 0 0   Completed
7 PIER Muthambi  SIDE 9 8 1 0 1 1 0 0   Completed
8 PIER Thamarassery SIDE 11 10 1 0 1 0 1 1 5 Work in progress.
9 PIER NH SIDE 10 9 1 0 1 0 1 1 3 Final lift shuttering work in progress.
10 PIER CAP Muthambi  SIDE 9 6 3 0 1 0 1 3 5 steel work in progress
11 PIER CAP Thamarassery SIDE 11 10 1 0 0 0 0 0    
12 PIER CAP NH SIDE 10 9 1 0 0 0 0 0    
13 RE/R WALL Muthambi side 100% 0 100% 0 0.00% 0.00% 0 0.00%    
14 RE/R WALL Thamarassery side SIDE 100% 35% 65% 0 10.00% 0.00% 0.1 10.00% 5 Raft& Side wall 1st lift done at one side.
15 RE/R WALL NH SIDE 100% 45% 65% 0 25.00% 10.00% 0.15 25.00% 5 Raft& Side wall 1st lift done .
16 BEAM/SLAB Muthambi SIDE 8 5 3 0 0 0 0 0    
17 BEAM/SLAB Thamarassery SIDE 10 7 3 0 2 0 2 2 5 staging work between  P23-P24& P19-P20 completed concreting on 25.06.12
18 BEAM/SLAB NH SIDE 11 7 4 0 0 0 0 0 6 shuttering work between  P7-P8 for deck in progress
19 HR/FP/KERB Muthambi SIDE 100% 0 100% 0 10.00% 10.00% 0 10.00%   Kerb casting&Hand rail fixing started
20 HR/FP/KERB thamarassery SIDE 100% 0 100% 0 0.00% 0.00% 0 0.00%    
21 HR/FP/KERB NH SIDE 100% 0 100% 0 0.00% 0.00% 0 0.00%    
22 BC/PAINTING 100% 0 100% 0 0.00% 0.00% 0 0.00%    
23 Utility shifting             0     KSEB utility shifting started. Shifted 1 post
                       
                       
                       
  Availbility of Men                     
  Date 16/6/2012 17/6/2012 18/6/2012 19/6/2012 20/6/2012 21/6/2012 22/6/2012      
  Nof labours 62 38 28 26 40 42 47      
                       
  Material Stocking Status Required Available Remarks              
  Coarse Aggreagate (m3) 50 60                
  Fine Aggreagate(m3) 50 40                
  Cement(bag) 1000 950                
  Steel(MT) 40 60                
                       
                       
  Utility shifting                    
  Utilities to be shifted Status Remarks                
  BSNL                    
  KSEB                    
  KWA                    
  Others                    
 
Back
 
    
WATER LOGGING NEAR RAILWAY PORTION

    
    
WATER LOGGING IN THAMARASSERY SIDE DUE TO RAIN

    
    
WATER LOGGING IN SITE

    
    
SHUTTERING WORK IN PROGRESS OF RETAINING WALL SECOND LIFT AT AP3

    
 
    
PIER WORK OBSTRUCTED DUE TO HEAVY RAIN AT T JUNCTION

    
    
P18 PILE CAP WORK IN PROGRESS

    
    
KERB WORK IN PROGRESS AT MUTHAMBI SIDE

    
 
    
GIRDER WORK IN PROGRESS P23-P24

    
    
GIRDER WORK IN PROGRESS P19-P20

      
 

 

 

 

 

 

 

 