   Weekly progress report as on 15.06.2012
    
weekly progress 15.6.2012                
                   
Progress Report For Anayara ROB for the week ending on 15.6.2012      
                   
Sl No  Activity Description  Total Quantity Cumulative progress upto 15.6.12 Balance  work up to 15.6.12 Cumulative delay in Qty up to 15.6.12 Work  planned  during the week  Actual work done during the week  Delay in Qty up to this week Work  Planned for next week 
1 PILE  Pettah side(Approach portion) 12 12 0 0 0 0 0 0
2 PILE Anayara side(Approach portion) 12 12 0 0 0 0 0 0
3 PILE CAP Pettah side(Approach portion) 4 4 0 0 0 0 0 0
4 PILE CAP Anayara side(Approach portion) 4 4 0 0 0 0 0 0
5 PIER Pettah side(Approach portion) 4 4 0 0 0 0 0 0
6 PIER Anayara side(Approach portion) 4 4 0 0 0 0 0 0
7 PIER  CAP Pettah side(Approach portion) 4 4 0 0 0 0 0 0
  PIER  CAP Anayara side(Approach portion) 4 4 0 0 0 0 0 0
8 GIRDER Pettah side(Approach portion) 4 0.5 3.5     0.5   0.5
9 GIRDER Anayara side(Approach portion) 4 2 2          
10 Service Road Pettah side(Approach portion) 1400 350 1050          
11 Service Road Anayara side(Approach portion) 1400 350 1050          
12 RT Wall Pettah side(Approach portion) % 100 88 12          
13 RT Wall Anayara side(Approach portion) % 100 88 12                
14 RE Wall Panel Casting Pettah side(Approach portion) 400 400 0          
15 RE Wall Panel Casting Anayara side(Approach portion) 400 350 50     34    
16 RE Wall Panel Erection Pettah side(Approach portion) 400 164 236     82    
17 RE Wall Panel Erection Anayara side(Approach portion) 400 296 104     74    
 