Untitled Document
Road to Prosperity
Site last updated on:  12-12-2020 | You are visitor: 7887107
Completed Projects Projects Under Construction Citizen Services Careers Right to Service


Prevoius Weekly Reports

   Weekly progress report as on 15.06.2012
    
Si No  Activity Description  Total Quantity Cumulative progress upto last week  Balance  work up to last week Cumulative delay in Qty up to last week Work  planned  during the week  Actual work done during the week  Cumulative delay in Qty up to this week Work  Planned for next week  No of days remaining for completion as per the weekly plan Remarks 
1 PILE Muthambi side 27 27 0 0 0 0 0 0   Completed
2 PILE Thamarassery side 33 33 0 0 0 0 0 0   Completed
3 PILE NH SIDE 33 33 0 0 0 0 0 0   Completed
4 PILE CAP Muthambi SIDE 9 9 0 0 0 0 0 0   Completed
5 PILE CAP Thamarassery SIDE 11 10 1 0 1 0 1 1 3 Work in progress.
6 PILE CAP NH SIDE 10 10 0 0 0 0 0 0   Completed
7 PIER Muthambi  SIDE 9 8 3 0 1 0 1 1   Work in progress.
8 PIER Thamarassery SIDE 11 10 1 0 1 0 1 0   Work in progress.
9 PIER NH SIDE 10 9 1 0 1 0 1 1   Work in progress.
10 PIER CAP Muthambi  SIDE 9 6 3 0 0 0 0 1    
11 PIER CAP Thamarassery SIDE 11 10 1 0 0 0 0 0    
12 PIER CAP NH SIDE 10 9 1 0 0 0 0 0    
13 RE/R WALL Muthambi side 100% 0 100% 0 0.00% 0.00% 0 0.00%    
14 RE/R WALL Thamarassery side SIDE 100% 30% 70% 0 10.00% 5.00% 0.05 10.00% 5 Raft& Side wall 1st lift done at one side.steel work in progress
15 RE/R WALL NH SIDE 100% 40% 65% 0 25.00% 5.00% 0.2 25.00% 5 Raft COMPLETED.Shuttering work in progress
16 BEAM/SLAB Muthambi SIDE 8 5 3 0 0 0 0 0    
17 BEAM/SLAB Thamarassery SIDE 10 6 4 0 1 1 0 2 5 staging work between  P23-P24& P19-P20 completed concreting on 20.06.12
18 BEAM/SLAB NH SIDE 11 7 4 0 0 0 0 0 6 shuttering work between  P7-P8 for deck in progress
19 HR/FP/KERB Muthambi SIDE 100% 0 100% 0 0.00% 0.00% 0 0.00%   Hand rail fixing started
20 HR/FP/KERB thamarassery SIDE 100% 0 100% 0 0.00% 0.00% 0 0.00%    
21 HR/FP/KERB NH SIDE 100% 0 100% 0 0.00% 0.00% 0 0.00%    
22 BC/PAINTING 100% 0 100% 0 0.00% 0.00% 0 0.00%    
23 Utility shifting             0     KSEB utility shifting started. Shifted 1 post
                       
                       
                       
  Availbility of Men                     
  Date 06-09-2012 06-10-2012 06-11-2012 06-12-2012 13/6/2012 14/6/2012 15/6/2012      
  Nof labours 70 50 70 25 0 42 65      
                       
  Material Stocking Status Required Available Remarks              
  Coarse Aggreagate (m3) 50 75                
  Fine Aggreagate(m3) 50 75                
  Cement(bag) 1000 1200                
  Steel(MT) 40 50                
                       
                       
  Utility shifting                    
  Utilities to be shifted Status Remarks                
  BSNL                    
  KSEB                    
  KWA                    
  Others                    
 
Back
 
    
SHUTTERING P23-P24

    
    
SHUTTERING IN PROGRESS P19-P20

    
    
RETAINING WALL WORK IN PROGRESS AT NH SIDE

    
    
PIER P9B

    
 
    
LONG VIEW OF ROB

    
    
COMPOSITE GIRDER WELDING WORK IN PROGRESS BY RAILWAY

      
 

 

 

 

 

 

 

 

Untitled Document