Prevoius Weekly Reports

   Weekly progress report as on 15.06.2012
    
Sl.No Activity Description Total Quantity Cumulative Progress upto last week Balance work up to last week Cumulative delay in Qty up to last week Work planned during the week Actual work done during the week Cumulative delay in Qty up to this week Work planned for the next week
1 Piles 63 63 - - - - - -
2 Pile cap 21 21 - - - - - -
3 Pier  21 21 - - - - - -
4 PierCap 21 16 5 - 1 1 0 1
5 Deck Slab 21 7 14 - 0 0 0 1
6 RC wall - Kuttipuram side 100% 25% 75% - 3% 5% -2% 4%
                   
Date 09.06.12 11.06.12 12.06.12 13.06.12 14.06.12 15.06.12      
Climate Pleasant Pleasant Rain Rain Rain Rain      
No. of labours 57 57 55 55 57 57      
                   
                   
Availability of Materials                
Material Required Available              
Fine aggregate 24 m3 26m3              
Coarse Aggregate 35 m3 41 m3              
Cement 130bags 350 bags              
Steel 25MT 30MT              
 
Back
 
    
BEAM REINFORCEMENT WORKS COMPLETED IN P14-P15

    
    
PIER CAP REINFORCEMENT IN P7

    
    
PIER CAP COCRETING P7

    
    
BEAM REINFORCEMENT IN P14-P15

    
 
 
 

 

 

 

 

 

 

 