Prevoius Weekly Reports

   Weekly progress report as on 15.06.2012
    
Si No  Activity Description  Total Quantity Cumulative progress upto last week  Balance  work up to last week Cumulative delay in Qty up to last week Work  planned  during the week  Actual work done during the week  Cumulative delay in Qty up to this week Work  Planned for next week  No of days remaing for completion as per the weekly plan
1 PILE  CALICUT  SIDE 48 48 0 1 0 0 1 0  
2 PILE THIRUR SIDE 24 24 0 11 0 0 11 0  
3 PILE CAP CALICUT  SIDE 12 12 0 1 0 0 1 0  
4 PILE CAP  THIRURSIDE 6 6 0 5 0 0 5 0  
5 PIER CALICUT SIDE 12 12 0 1 0 0 1 0  
6 PIER THIRUR SIDE 6 6 0 1 0 0 1 0  
7 PIER CAPCALICUT   SIDE 12 12 0 2 0 0 2 0  
8 PIER CAP THIRUR SIDE 6 6 0 3 0 0 3 0  
9 RETAINING WALL WALL CALICUT   SIDE 100% 65.00% 35% 0 5.00% 0.00% 30.00% 0.00%  
10 RETAINING WALL THIRUR SIDE 100% 10% 90% 0 10.00% 5.00% 20.00% 10.00%  
11 BEAM CALICUT   SIDE 12 6 6 0 0 0 4 0  
12 SLAB CALICUT SIDE 12 4 8   1 1 6 1  
13 BEAM THIRUR SIDE 6 1 5 0 1 1 5 1  
14 SLAB TIRUR SIDE               1  
15 HR/FP/KERB CALICUT   SIDE 100% 0 100% 0 0.00% 0.00% 0.00% 0.00%  
16 HR/FP/KERBTHIRUR SIDE 100% 0 100% 0 0.00% 0.00% 0.00% 0.00%  
17 BC/PAINTING 100% 0 100% 0 0.00% 0.00% 0.00% 0.00%  
18 Deck Slab                  
17 Utility shifting                  
                     
                     
                     
  Availbility of Men                 
  Date 09-06-2012 10-06-2012 11-06-2012 12-06-2012 13-06-2012 14-06-2012 15-06-2012    
  Nof labours 54 54 54 54 54 57 57    
                     
  Material Stocking Status Required Available Remarks            
  Coarse Aggreagate (m3)       RMC          
  Fine Aggreagate(m3)                  
  Cement(bag)                  
  Steel(MT)   14              
                     
                     
  Utility shifting                  
  Utilities to be shifted Status Remarks              
  BSNL shifting completed                
  KSEB shifting in progress                
  KWA shifting completed                
  Others                  
 
Back
 
    
STAGING @ P13-P14

    
    
SLAB WORKS IN PROGRESS @ P6-P7

    
    
RETAINING WALL @ TIRUR SIDE CONCRETE

    
    
GIRDER REINFORCEMENT P16-A2

    
 
    
DESHUTTERING P14-P15

      
 

 

 

 

 

 

 

 