Prevoius Weekly Reports

   Weekly progress report as on 15.06.2012
    
Sl No  Activity Description  Total Quantity Cumulative progress upto last week  Balance  work up to last week Cumulative delay in Qty up to last week Work  planned  during the week  Actual work done during the week  Cumulative delay in Qty up to this week Work  Planned for next week  No of days remaing for completion as per the weekly plan Remarks 
1 PILE CHERUVATHOOR  SIDE 27 27 Completed    
2 PILE PADANNA SIDE 24 24 Completed    
3 PILE CAP CHERUVATHOOR SIDE 9 9 Completed    
4 PILE CAP  PADANNA SIDE 8 8 Completed    
5 PIER CHERUVATHOOR SIDE 9 9 Completed    
6 PIER PADANNA SIDE 8 8 Completed    
7 PIER CAP CHERUVATHOOR SIDE 9 9 Completed    
8 PIER CAP PADANNA SIDE 8 8 Completed    
9 RE/RC WALL CHERUVATHOOR  SIDE 100% 80% 20% 20% 5.00% 0.00% 20.00% 0.00%   RE Panel works held up due to rain and unavailability of red earth
10 RE/RC  WALL PADANNA SIDE 100% 23% 77% 15% 15.00% 10.00% 5.00% 10.00%   RC Wall LHS-Raft complete and wall first lift complete for 15 m.
11 BEAM/SLAB CHERUVATHOOR  SIDE 9 6 3 1 0.5 0 1 0.5   Reinf in progress for P10-P9 Girder.
12 BEAM/SLAB PADANNA SIDE 8 7 1 complete except railway adjacent span    
13 EXPANSION JOINT CHERUVATHUR SIDE 9 5 4 0 0 0 0 0    
14 EXPANSION JOINT PADANNA SIDE 8 0 8 0 2 0 2 3    
15 KERB CHERUVATHOOR  SIDE 100% 67.50% 33% 0 0.00% 0.00% 0.00% 0.00%   kerb complete for AP2-P10 spans
16 KERB PADANNA SIDE 100% 0 100% 0 24.00% 0.00% 24.00% 36.00%   3 spans planned
17 HANDRAIL CHERUVATHUR SIDE 100% 45% 55% 0 0.00% 0.00% 0.00% 0.00%   complete for AP2-P10 spans
18 HANDRAIL PADANNA SIDE 100% 0 100% 0 12.00% 0.00% 12.00% 0.00%    
17 BC/PAINTING 100% 0 100% 0 0.00% 0.00% 0.00% 0.00%    
18 Others                   Drainage works complete for 40m at chr side.
19 Deck Slab                    
20 Utility shifting                    
                       
                       
                       
  Availbility of Men                     
  Date 09-06-2012 10-06-2012 11-06-2012 12-06-2012 13-06-2012 14-06-2012 15-06-2012      
  No of labours 61 52 62 74 5 70 68      
                       
  Material Stocking Status Required Available Remarks              
  Coarse Aggreagate (m3) available                
  Fine Aggreagate(m3) available                
  Cement(bag) 500 600                
  Steel(MT) 10 7 shortage at site            
                       
                       
  Utility shifting                    
  Utilities to be shifted Status Remarks                
  BSNL work in progress at Padanna side RC wall area.            
  KSEB in progress electric post infront of unity hospital need to be shifted urgently.            
  KWA currently can be managed at site                   
  Others                    
 
Back
 
    
RC WALL SHUTTERING WORKS

    
    
RC WALL IP AT PADANNA SIDE LHS

    
    
P10-P9 GIRDER REINF IP

    
    
KERB SHUTTERING IP FOR P1-P2 SPAN

    
 
    
HANDRAILS AT CHR SIDE

    
    
DRAINAGE WORKS IP AT CHR SIDE

      
 

 

 

 

 

 

 

 