   Weekly progress report as on 08.06.2012
    
Sl No  Activity Description  Total Quantity Cumulative progress upto last week  Balance  work up to last week Cumulative delay in Qty up to last week Work  planned  during the week  Actual work done during the week  Cumulative delay in Qty up to this week Work  Planned for next week  No of days remaing for completion as per the weekly plan Remarks 
1 PILE CHERUVATHOOR  SIDE 27 27 Completed    
2 PILE PADANNA SIDE 24 24 Completed    
3 PILE CAP CHERUVATHOOR SIDE 9 9 Completed    
4 PILE CAP  PADANNA SIDE 8 8 Completed    
5 PIER CHERUVATHOOR SIDE 9 9 Completed    
6 PIER PADANNA SIDE 8 8 Completed    
7 PIER CAP CHERUVATHOOR SIDE 9 9 Completed    
8 PIER CAP PADANNA SIDE 8 8 Completed    
9 RE/RC WALL CHERUVATHOOR  SIDE 100% 80% 20% 20% 5.00% 0.00% 20.00% 5.00%   RE Panel works held up due to rain and unavailability of red earth
10 RE/RC  WALL PADANNA SIDE 100% 21% 79% 10% 10.00% 2.00% 15.00% 15.00%   RC Wall RHS-raft and first lift for wall portion complete, LHS raft reinf in progress
11 BEAM/SLAB CHERUVATHOOR  SIDE 9 6 3 1 0 0 1 0.5   Bottom shuttering in progress for P10-P9 girder
12 BEAM/SLAB PADANNA SIDE 8 7 1 complete except railway adjacent span    
13 EXPANSION JOINT CHERUVATHUR SIDE 9 5 4 0 0 0 0 0    
14 EXPANSION JOINT PADANNA SIDE 8 0 8 0 0 0 0 2    
15 KERB CHERUVATHOOR  SIDE 100% 67.50% 33% 0 0.00% 0.00% 0.00% 0.00%   P12-P11,P11-P10 span kerb complete
16 KERB PADANNA SIDE 100% 0 100% 0 0.00% 0.00% 0.00% 24.00%   2 spans planned
17 HANDRAIL CHERUVATHUR SIDE 100% 30% 70% 0 15.00% 15.00% 0.00% 0.00%   P12-P11,P11-P10 spans complete
18 HANDRAIL PADANNA SIDE 100% 0 100% 0 0.00% 0.00% 0.00% 12.00%    
17 BC/PAINTING 100% 0 100% 0 0.00% 0.00% 0.00% 0.00%    
16 Deck Slab                    
17 Utility shifting                    
                       
                       
                       
  Availbility of Men                     
  Date 02-06-2012 03-06-2012 04-06-2012 05-06-2012 06-06-2012 07-06-2012 08-06-2012      
  No of labours 60 60 63 63 64 63 63      
                       
  Material Stocking Status Required Available Remarks              
  Coarse Aggreagate (m3) available                
  Fine Aggreagate(m3) available                
  Cement(bag) 500 720                
  Steel(MT) 10 15              
                       
                       
  Utility shifting                    
  Utilities to be shifted Status Remarks                
  BSNL work in progress at Padanna side RC wall area.            
  KSEB in progress electric post infront of unity hospital need to be shifted urgently.            
  KWA currently can be managed at site                   
  Others                    
 
Back
 
    
STAGING WORKS AT P9-P8

    
    
RC WALL REINFORCEMENT IN PROGRESS

    
    
DRAINAGE WORK IN PROGRESS AT CHR SIDE

    
    
CHR SIDE RE PANEL WORKS AFFECTED BY RAIN

    
 
 
 

 

 

 

 

 

 

 