PROGRESS REPORT (upto June 1st 2012)
RAILWAY PORTION
Total scope: 4 Locations
LOCATIONS:P1,P7 ,P8,P2
P1,P7 –N.H side
P8,P2-Pulikkakadavu side.
Total Piles: 18
No of PILES IN EACH LOCATION
P1 location: 4
P7 location:5
P8 location:5
P2 location:4
WORK COMPLETED IN EACH LOCATION OF RAILWAY PORTION
P1 location:Piling completed (4 piles),pile cap,trestle column,trestle beam.
P7 location:5 pile concreting completed,pile cap,trestle column,trestle beam
P8 location:Piling completed(5 piles),pile cap,Trestle column,trestle beam
P2 location:Piling completed(4 piles),pile cap,trestle column,trestle beam.
Approach portion at N.H side completed 60%
WORK COMPLETED AT PULIKKAKADAVU SIDE
All deck slab concreting completed at pulikkakadavu side.
Works completed upto the roadworks,miscellaneous works, in the approach portion at pulikkakadavu side.
WORKS BALANCE
P1-P7 superstructure (RCC structure)
P7-P8 superstructure( CENTRAL SPAN)
P8-P2 superstructure (RCC structure)
|