Untitled Document
Road to Prosperity
Site last updated on:  12-12-2020 | You are visitor: 8053109
Completed Projects Projects Under Construction Citizen Services Careers Right to Service


Prevoius Weekly Reports

   Weekly progress report as on 01.06.2012
    
Si No  Activity Description  Total Quantity Cumulative progress upto 31.05.12 Balance  work up to 31.05.12 Cumulative delay in Qty up to 31.05.12 Work  planned  during the week  Actual work done during the week delay in Qty up to this week Work  Planned for next week  No of days remaing for completion as per the weekly plan Remarks 
1 PILE  Palarivattom side(Approach portion) 31 31 0 0 2 2 0 0   KWA line to be shifted. Will be over by 18.01.12. work completed on 23.01.12.Rig erected at P9
2 PILE Palarivattom side(railway portion) 6 6 0 0 1 0 1 1
3 PILE vytilla side(Approach portion) 42 42 0 0 0 0 0 0   Pipe line broken on 26.01.12 at 2.20 am while boring.Repaired on 26.01.12
4 PILE vytilla side(railway portion) 6 5 1 0 0 0 0 1   RP1 P4 done . RP1 P5 was abandoned due to pile choking. Pile layout to be redesigned.Piling resumed on 29.02.12. Piling held up pending approval  fron RLY
5 PILE CAP Palarivattom side(Approach portion) 8 8 0 0 0 0 0 0   KWA line to be shifted. Will be over by 18.01.12. work completed on 23.01.12.
6 PILE CAP Palarivattom side(railway portion) 1 0 1 0 0 0 0 0
7 PILE CAP vytilla side(Approach portion) 9 9 0 0 0 0 0 0   P1,  P2, P4, P3, A1, P5,P6, P7,P8
8 PILE CAP vytilla side(railway portion) 1 0 1 0 0 0 0 0    
9 PIER Palarivattom side(Approach portion) 8 7 1 0 1 0 1 1   A2, P15, P14, P13,  P12,  P11, P10 
10 PIER Palarivattomside(railway portion) 1 0 1 0 0 0 0 0    
11 PIER Vytilla side(Approach portion) 9 9 0 0 2 0 0 0 "      " P1, P2, P3, P4, A1,P5,P6,P7, P8
12 PIER vytilla side(railway portion) 1 0 1 0 0 0 0 0 "      "  
13 PIER  CAP Palarivattom side(Approach portion) 8 7 1 0 0 0 0 0   P15, P14, A2, P13, P12, P11, P10
14 PIER  CAP Vytila side(Approach portion) 9 8 1 0 1 1 0 1   P1, P2, P3, A1,P4,P5,P6,P7
15 GIRDER Palarivattom side(Approach portion) 7 6 1 0 0 0 0 0   A2 P15,P15 P14,P14 P13, P13 P12, P11 P10, P12 P11
16 GIRDERVytila side(Approach portion) 9 3.66 5.34 0 1 1 0 0.34   P1 P2,  A1P1, P2P3, P3P4
17 DECK SLAB Palarivattom side(Approach portion) 7 6 1 0 1 0 1 0   A2 P15, P15 P14, P14 P13,  P13 P12, P11P10, P12 P11
18 DECK SLABVytila side(Approach portion) 9 2 7 0 0 0 0 1   P1P2,A1P1
19 PIER CAP Palarivattomside(railway portion) 1 0 1 0 0 0 0 0    
20 PIER CAP vytilla side(railway portion) 1 0 1 0 0 0 0 0    
21 RE WALL PANEL 351 351 0 0 0 0 0 0    
20 RE WALL PCC Palarivattom 95 95 0 0 0 0 0 0   Rerouting of water connection to photostat shop  by KWA to the completed on 24.03.12. on 24.04.12 the entire RE Wall area was cleared for excavation.
21 RE WALL Panel erection Palarivattom 100% 15% 0.85 0 60% 0 0 0   Rerouting of water connection to photostat shop  by KWA to the completed on 24.03.12. on 24.04.12 the entire RE Wall area was cleared for excavation.Panel erection commenced on 15.05.12
21 RE WALL Earth filling 100% 5% 0.95 0 60% 0 0 0   Rerouting of water connection to photostat shop  by KWA to the completed on 24.03.12. on 24.04.12 the entire RE Wall area was cleared for excavation.Panel erection commenced on 15.05.12
                       
  Remarks                    
                       
                       
                       
  Labour Report                    
                       
  Date 25.05.12 26.05.12 27.05.12 28.05.12 29.05.12 30.05.12 31.05.12      
  Day Fri Sat Sun Mon Tue Wed Thurs      
  Climate sunny  sunny  sunny  sunny sunny  sunny   sunny      
  No.of labours 65 64 47 61 64 66 65      
                       
  Availability of Material                     
                       
  Materials Required for week ending on 07.06.12 Available as on 01.06.12                
  Fine aggregate(M3) Ready Mix Concrete                
  Coarse aggregate(M3)                
  Cement(BAG)                
  Steel(TONN) 8 40                
 
Back
 
    
RE WALL PANEL ERECTION

    
    
HAND RAIL A2 P15

    
    
GIRDER P3P4

    
    
FILLING OF FILTER MEDIA

    
 
    
DECK SHUTTERING P2P3

    
    
BORING AT RP1 P5

    
    
RE WALL EARTH FILING

    
 
    
HANDRAIL SHOE A2P15

    
    
GIRDER P2 P3 DESHUTTERING

    
    
DECK RFT A1P1

    
 
 
 

 

 

 

 

 

 

 

Untitled Document