ROB at Koratty
PROGRESS OF ROB WORK AS ON 04.09.2010 |
Description |
Completed/ Progress |
Remarks |
Approval of GAD by railways (Railway Portion) |
Approved |
Approved on 1-5-10 |
Design and Drawing |
Submitted |
Approval pending with Railways |
Retaining wall concreting |
In progress |
|
Road Excavation for under pass |
Completed |
|
|