   Weekly Progress report as on 01.06.2012
    
Sl No  Activity Description  Total Quantity Cumulative progress upto last week  Balance  work up to last week Cumulative delay in Qty up to last week Work  planned  during the week  Actual work done during the week  Cumulative delay in Qty up to this week Work  Planned for next week  No of days remaing for completion as per the weekly plan Remarks 
1 PILE CHERUVATHOOR  SIDE 27 27 Completed    
2 PILE PADANNA SIDE 24 24 Completed    
3 PILE CAP CHERUVATHOOR SIDE 9 9 Completed    
4 PILE CAP  PADANNA SIDE 8 8 Completed    
5 PIER CHERUVATHOOR SIDE 9 9 Completed    
6 PIER PADANNA SIDE 8 8 Completed    
7 PIER CAP CHERUVATHOOR SIDE 9 9 Completed    
8 PIER CAP PADANNA SIDE 8 8 Completed    
9 RE/RC WALL CHERUVATHOOR  SIDE 100% 80% 20% 20% 5.00% 0.00% 20.00% 5.00%   RE Panel 5th layer in progress,RC Wall 100% complete,RE Panel works held up due to unavailability of red earth
10 RE/RC  WALL PADANNA SIDE 100% 11% 89% 10% 10.00% 10.00% 10.00% 10.00%   RC Wall RHS-raft and first lift for wall portion complete
11 BEAM/SLAB CHERUVATHOOR  SIDE 9 6 3 1 0 0 1 0   staging complete for P8-P9 and P9-P10 girder
12 BEAM/SLAB PADANNA SIDE 8 6.5 1.5 0.5 0.5 0.5 0 0    AP1-P1 Deck slab complete,deck slabs complete at Padanna side
13 EXPANSION JOINT CHERUVATHUR SIDE 9 3 6 1 2 2 0 0   P12,P11 locations 
14 EXPANSION JOINT PADANNA SIDE 8 0 8 0 0 0 0 0    
15 KERB CHERUVATHOOR  SIDE 100% 52.50% 48% 0 15.00% 15.00% 0.00% 0.00%   P12-P11,P11-P10 span kerb complete
16 KERB PADANNA SIDE 100% 0 100% 0 0.00% 0.00% 0.00% 0.00%    
17 HANDRAIL CHERUVATHUR SIDE 100% 15% 85% 0 15.00% 15.00% 0.00% 15.00%   P14-P13,P13-P12 span complete
18 HANDRAIL PADANNA SIDE 100% 0 100% 0 0.00% 0.00% 0.00% 0.00%    
17 BC/PAINTING 100% 0 100% 0 0.00% 0.00% 0.00% 0.00%    
16 Deck Slab                    
17 Utility shifting                    
                       
                       
                       
  Availbility of Men                     
  Date 26-05-2012 27-05-2012 28-05-2012 29-05-2012 30-05-2012 31-05-2012 01-06-2012      
  No of labours 69 63 73 70 64 64 63      
                       
  Material Stocking Status Required Available Remarks              
  Coarse Aggreagate (m3) available                
  Fine Aggreagate(m3) available                
  Cement(bag) 400 1000                
  Steel(MT) 10 17              
                       
                       
  Utility shifting                    
  Utilities to be shifted Status Remarks                
  BSNL work to be started immediately at padanna side approach portion.AP1-P1 Location cleared for deck slab.            
  KSEB in progress electric post infront of unity hospital need to be shifted urgently.            
  KWA currently can be managed at site                   
  Others                    
 