Prevoius Weekly Reports

   Weekly Progress report as on 25/05/2012
    
Sl No   Activity Description   Total Quantity  Cumulative progress upto last week   Balance  work up to last week  Cumulative delay in Qty up to last week  Work  planned  during the week   Actual work done during the week   Cumulative delay in Qty up to this week  Work  Planned for next week   Remarks 
1 Pile towards NH side 26 26 0 0 0 0 0 0 TARGET ACHIEVED
2 Pile towards Puliyanam side 18 18 0 0 0 0 0 0 TARGET ACHIEVED
3 Pile cap at NH  Side 6 6 0 0 0 0 0 0 TARGET ACHIEVED
4 Pile Cap at Puliyanamside 4 4 0 0 0 0 0 0 TARGET ACHIEVED
5 RC wall at Puliyanam side 100% 100% 0 0 0 0 0 0 TARGET ACHIEVED
6 RC wall at NH side 100% 100% 0 0 0 0 0 0 TARGET ACHIEVED
7 Pier at NH Side 6 6 0 0 0 0 0 0 TARGET ACHIEVED
8 Pier at Puliyanam Side 4 4 0 0 0 0 0 0 TARGET ACHIEVED
9 Piercap at NH Side 6 6 0 0 0 0 0 0 TARGET ACHIEVED
10 Piercap at Puliyanam 4 4 0 0 0 0 0 0 TARGET ACHIEVED
11 PEDESTAL 54 54 0 0 0 0 0 0 TARGET ACHIEVED
12 Beam and cross beam at NH side 6 5 1 0 0 0 0 0 TARGET ACHIEVED (EXCLUDING RAILWAY ADJACENT SPAN) 
13 Beam and cross beam at Puliyanam side  4 3 1 0 0 0 0 0 TARGET ACHIEVED (EXCLUDING RAILWAY ADJACENT SPAN) 
14 Deck slab  at NH side  6 4 2 0 1 1 0 0 TARGET ACHIEVED (EXCLUDING RAILWAY ADJACENT SPAN) 
15 Deck slab  at Puliyanam side  4 3 1 0 0 0 0 0 TARGET ACHIEVED (EXCLUDING RAILWAY ADJACENT SPAN) 
16 Dirt wall  2 2 0 0 0 0 0 0 TARGET ACHIEVED (EXCLUDING RAILWAY ADJACENT SPAN) 
17 Kerb NH side 100% 45% 55% 0 10% 5% 0% 10%  
18 Kerb Puliyanam side 100% 85% 15% 0 0% 0% 0% 0% TARGET ACHIEVED (EXCLUDING RAILWAY ADJACENT SPAN) 
19 Earth filling in approach embankment  100% 100% 0% 0 25% 25% 0% 0% TARGET ACHIEVED
                     
Date 19.05.12 21.05.12 22.05.12 23.05.12 25.05.12          
Climate pleasant pleasant pleasant pleasant pleasant          
No.of labours 54 53 52 54 72          
                     
availability of material                    
materials Required Available                
Fine aggregate(M3) 30 45                
Coarse aggregate(M3) 40 55                
Cement(BAG) 500 700                
Steel(TONN) 10 30                
 
Back
 
    
SLAB P10-A2 REINFORCEMENT WORK, 23.05.2012

    
    
SLAB P10-A2 CONCRETE, 25.05.2012

    
    
PULIYANAM SIDE ROAD WORK,23.05.12

    
    
NH SIDE RC WALL EARTH FILLING, 21.05.2012

    
 
    
HAND RAIL FIXING ,22.05.2012

      
 

 

 

 

 

 

 

 