Description |
Completed/ Progress |
Remarks |
ROB at Parappanangady |
|
|
Pier cap (Total no of pier Cap- 21) |
Completed |
21 NOS COMPLETED |
RE Wall panel casting ( total600 nos) |
Completed |
Errection completed. |
Slab calicut side (total 10 nos ) |
In progress |
9nos done (adjacent span pending ) |
slab NH side ( 11 nos) |
In progress |
10nos done (adjacent span pending ) |
Retaining wall NH side |
completed |
completed |
Retaining wall calicut side |
completed |
completed |
Dirt wall AP2 concreting |
completed |
Done 100% |
Dirt wall AP1 concreting |
completed |
Done 100% |
Handrail casting |
completed |
1400 nos completed. |
Handrail fixing |
completed |
NH side 10 slab completed.Approach portion completed. |
Handrail fixing |
completed |
CALICUT side 9 span over.Approach portion completed. |
Pilling work RLY PORTION |
Completed |
PILING COMPLETED |
Pile cap RP1 |
Completed |
pier completed,piercap work in progress. |
Pile cap RP2 |
Completed |
pier completed. |
Pile cap RP3 |
Completed |
Pier started. |
Pile cap RP4 |
Completed |
Pilecap completed |
NH side RE panel erection |
completed |
100% completed. |
RE wall work calicut side. |
completed |
100% completed. |
expansion joint |
completed |
completed. |
painting-slab |
In progress |
95% completed. |