   Weekly progress Report as on 25.05.12
    
Si No  Activity Description  Total Quantity Cumulative progress upto last week  Balance  work up to last week Cumulative delay in Qty up to last week Work  planned  during the week  Actual work done during the week  Cumulative delay in Qty up to this week Work  Planned for next week  No of days remaining for completion as per the weekly plan Remarks 
1 PILE Muthambi side 27 27 0 0 0 0 0 0    
2 PILE Thamarassery side 33 33 0 0 0 0 0 0    
3 PILE NH SIDE 33 33 0 0 0 0 0 0    
4 PILE CAP Muthambi SIDE 9 6 3 0 1 0 1 3 5 Work in progress.
5 PILE CAP Thamarassery SIDE 11 10 1 0 1 0 1 1 5 Work in progress.
6 PILE CAP NH SIDE 10 9 1 0 0 0 0 1 5 Work in progress.
7 PIER Muthambi  SIDE 9 6 3 0 0 0 0 2    
8 PIER Thamarassery SIDE 11 10 1 0 0 0 0 1    
9 PIER NH SIDE 10 9 1 0 0 0 0 0    
10 PIER CAP Muthambi  SIDE 9 6 3 0 0 0 0 0    
11 PIER CAP Thamarassery SIDE 11 9 2 0 1 0 1 1 2 steel work completed
12 PIER CAP NH SIDE 10 9 1 0 0 0 0 0    
13 RE/R WALL Muthambi side 100% 0 100% 0 0.00% 0.00% 0 0.00%    
14 RE/R WALL Thamarassery side SIDE 100% 15% 85% 0 10.00% 5.00% 0.05 25.00% 5 Raft done at one side.steel work in progress
15 RE/R WALL NH SIDE 100% 35% 65% 0 25.00% 0.00% 0.25 25.00% 5 Raft COMPLETED.Shuttering work in progress
16 BEAM/SLAB Muthambi SIDE 8 5 3 0 0 0 0 0    
17 BEAM/SLAB Thamarassery SIDE 10 4 6 0 2 1 1 1 3 shuttering work between  P27-AP3 for girder in progress
18 BEAM/SLAB NH SIDE 11 6 5 0 0 0 0 1 5 shuttering work between  P7-P8 for girder in progress
19 HR/FP/KERB Muthambi SIDE 100% 0 100% 0 0.00% 0.00% 0 0.00%   Hand rail fixing started
20 HR/FP/KERB thamarassery SIDE 100% 0 100% 0 0.00% 0.00% 0 0.00%    
21 HR/FP/KERB NH SIDE 100% 0 100% 0 0.00% 0.00% 0 0.00%    
22 BC/PAINTING 100% 0 100% 0 0.00% 0.00% 0 0.00%    
23 Utility shifting             0     KSEB utility shifting started. Shifted 1 post
 
Back
 
    
RETAINING WALL RAFT AT WIRK IN PROGRESS AP3 SIDE

    
    
PILE CHIPPING IN PROGRESS AT P17

    
    
P21-P22 DECK SLAB CONCRETING

    
    
P19 PIER CAP WORK IN PROGRESS

    
 
    
HAND RAIL WORK JUST STARTED AT AP2 SIDE

    
    
GIRDER WORK IN PROGRESS P7-P8

      
 

 

 

 

 

 

 

 