Si No |
Activity Description |
Total Quantity |
Cumulative progress upto last week |
Balance work up to last week |
Cumulative delay in Qty up to last week |
Work planned during the week |
Actual work done during the week |
Cumulative delay in Qty up to this week |
Work Planned for next week |
No of days remaining for completion as per the weekly plan |
Remarks |
1 |
PILE Muthambi side |
27 |
27 |
0 |
0 |
0 |
0 |
0 |
0 |
|
|
2 |
PILE Thamarassery side |
33 |
33 |
0 |
0 |
0 |
0 |
0 |
0 |
|
|
3 |
PILE NH SIDE |
33 |
33 |
0 |
0 |
0 |
0 |
0 |
0 |
|
|
4 |
PILE CAP Muthambi SIDE |
9 |
6 |
3 |
0 |
1 |
0 |
1 |
3 |
5 |
Work in progress. |
5 |
PILE CAP Thamarassery SIDE |
11 |
10 |
1 |
0 |
1 |
0 |
1 |
1 |
5 |
Work in progress. |
6 |
PILE CAP NH SIDE |
10 |
9 |
1 |
0 |
0 |
0 |
0 |
1 |
5 |
Work in progress. |
7 |
PIER Muthambi SIDE |
9 |
6 |
3 |
0 |
0 |
0 |
0 |
2 |
|
|
8 |
PIER Thamarassery SIDE |
11 |
10 |
1 |
0 |
0 |
0 |
0 |
1 |
|
|
9 |
PIER NH SIDE |
10 |
9 |
1 |
0 |
0 |
0 |
0 |
0 |
|
|
10 |
PIER CAP Muthambi SIDE |
9 |
6 |
3 |
0 |
0 |
0 |
0 |
0 |
|
|
11 |
PIER CAP Thamarassery SIDE |
11 |
9 |
2 |
0 |
1 |
0 |
1 |
1 |
2 |
steel work completed |
12 |
PIER CAP NH SIDE |
10 |
9 |
1 |
0 |
0 |
0 |
0 |
0 |
|
|
13 |
RE/R WALL Muthambi side |
100% |
0 |
100% |
0 |
0.00% |
0.00% |
0 |
0.00% |
|
|
14 |
RE/R WALL Thamarassery side SIDE |
100% |
15% |
85% |
0 |
10.00% |
5.00% |
0.05 |
25.00% |
5 |
Raft done at one side.steel work in progress |
15 |
RE/R WALL NH SIDE |
100% |
35% |
65% |
0 |
25.00% |
0.00% |
0.25 |
25.00% |
5 |
Raft COMPLETED.Shuttering work in progress |
16 |
BEAM/SLAB Muthambi SIDE |
8 |
5 |
3 |
0 |
0 |
0 |
0 |
0 |
|
|
17 |
BEAM/SLAB Thamarassery SIDE |
10 |
4 |
6 |
0 |
2 |
1 |
1 |
1 |
3 |
shuttering work between P27-AP3 for girder in progress |
18 |
BEAM/SLAB NH SIDE |
11 |
6 |
5 |
0 |
0 |
0 |
0 |
1 |
5 |
shuttering work between P7-P8 for girder in progress |
19 |
HR/FP/KERB Muthambi SIDE |
100% |
0 |
100% |
0 |
0.00% |
0.00% |
0 |
0.00% |
|
Hand rail fixing started |
20 |
HR/FP/KERB thamarassery SIDE |
100% |
0 |
100% |
0 |
0.00% |
0.00% |
0 |
0.00% |
|
|
21 |
HR/FP/KERB NH SIDE |
100% |
0 |
100% |
0 |
0.00% |
0.00% |
0 |
0.00% |
|
|
22 |
BC/PAINTING |
100% |
0 |
100% |
0 |
0.00% |
0.00% |
0 |
0.00% |
|
|
23 |
Utility shifting |
|
|
|
|
|
|
0 |
|
|
KSEB utility shifting started. Shifted 1 post |