   Weekly progress report as on 25.05.2012
    
Sl No  Activity Description  Total Quantity Cumulative progress upto last week  Balance  work up to last week Cumulative delay in Qty up to last week Work  planned  during the week  Actual work done during the week  Cumulative delay in Qty up to this week Work  Planned for next week  No of days remaing for completion as per the weekly plan Remarks 
1 PILE CHERUVATHOOR  SIDE 27 27 Completed    
2 PILE PADANNA SIDE 24 24 Completed   Piling works completed.
3 PILE CAP CHERUVATHOOR SIDE 9 9 Completed    
4 PILE CAP  PADANNA SIDE 8 8 Completed    
5 PIER CHERUVATHOOR SIDE 9 9 Completed    
6 PIER PADANNA SIDE 8 8 Completed    
7 PIER CAP CHERUVATHOOR SIDE 9 9 Completed    
8 PIER CAP PADANNA SIDE 8 8 Completed    
9 RE/RC WALL CHERUVATHOOR  SIDE 100% 75% 25% 15% 10.00% 5.00% 20.00% 5.00%   RE Panel 5th layer in progress,RC Wall 100% complete.
10 RE/RC  WALL PADANNA SIDE 100% 6% 94% 5% 5.00% 5.00% 10.00% 10.00%   Raft reinforcement in progress at RHS for RC Wall
11 BEAM/SLAB CHERUVATHOOR  SIDE 9 6 3 0 0 0 1 0   staging complete for P8-P9 and P9-P10 girder
12 BEAM/SLAB PADANNA SIDE 8 6 2 0.5 0.5 0.5 0 0.5    AP1-P1 Girder complete
13 EXPANSION JOINT CHERUVATHUR SIDE 9 3 6 1 1 0 1 2    
14 EXPANSION JOINT PADANNA SIDE 8 0 8 0 0 0 0 0    
15 KERB CHERUVATHOOR  SIDE 100% 22.50% 78% 0 15.00% 25.00% 0.00% 15.00%   P14-P13,P13-P12 span kerb complete,RC Wall kerb complete
16 KERB PADANNA SIDE 100% 0 100% 0 0.00% 0.00% 0.00% 0.00%    
17 HANDRAIL CHERUVATHUR SIDE 100% 0% 100% 0 7.50% 15.00% 0.00% 15.00%   P15-P14,AP2-P15 span complete
18 HANDRAIL PADANNA SIDE 100% 0 100% 0 0.00% 0.00% 0.00% 0.00%    
17 BC/PAINTING 100% 0 100% 0 0.00% 0.00% 0.00% 0.00%    
16 Deck Slab                    
17 Utility shifting                    
                       
                       
                       
  Availbility of Men                     
  Date 19-05-2012 20-05-2012 21-05-2012 22-05-2012 23-05-2012 24-05-2012 25-05-2012      
  No of labours 74 66 69 69 69 12 69      
                       
  Material Stocking Status Required Available Remarks              
  Coarse Aggreagate (m3) available                
  Fine Aggreagate(m3) available                
  Cement(bag) 750 1300                
  Steel(MT) 10 20              
                       
                       
  Utility shifting                    
  Utilities to be shifted Status Remarks                
  BSNL work to be started immediately at padanna side approach portion.AP1-P1 Location cleared for deck slab.            
  KSEB in progress electric post infront of unity hospital need to be shifted urgently.            
  KWA currently can be managed at site                   
  Others                    
 
Back
 
    
VIEW OF PADANNA SIDE

    
    
STAGING COMPLETE FOR P8-P9 AND P9-P10 SPAN

    
    
RE PANEL WORKS IN PROGRESS AT CHERUVATHUR SIDE

    
    
RC WALL RAFT REINF. IN PROGRESS AT RHS- PADANNA SIDE

    
 
    
KERBS AT CHERUVATHUR SIDE

    
    
KERB-P13-P12 SPAN

    
    
HANDRAILS OF AP2-P15 & P15-P14 SPAN

    
 
    
AP1-P1 GIRDER

      
 

 

 

 

 

 

 

 