Sl No |
Activity Description |
Total Quantity |
Cumulative progress upto last week |
Balance work up to last week |
Cumulative delay in Qty up to last week |
Work planned during the week |
Actual work done during the week |
Cumulative delay in Qty up to this week |
Work Planned for next week |
No of days remaing for completion as per the weekly plan |
Remarks |
1 |
PILE CHERUVATHOOR SIDE |
27 |
27 |
Completed |
|
|
2 |
PILE PADANNA SIDE |
24 |
24 |
Completed |
|
Piling works completed. |
3 |
PILE CAP CHERUVATHOOR SIDE |
9 |
9 |
Completed |
|
|
4 |
PILE CAP PADANNA SIDE |
8 |
8 |
Completed |
|
|
5 |
PIER CHERUVATHOOR SIDE |
9 |
9 |
Completed |
|
|
6 |
PIER PADANNA SIDE |
8 |
8 |
Completed |
|
|
7 |
PIER CAP CHERUVATHOOR SIDE |
9 |
9 |
Completed |
|
|
8 |
PIER CAP PADANNA SIDE |
8 |
8 |
Completed |
|
|
9 |
RE/RC WALL CHERUVATHOOR SIDE |
100% |
75% |
25% |
15% |
10.00% |
5.00% |
20.00% |
5.00% |
|
RE Panel 5th layer in progress,RC Wall 100% complete. |
10 |
RE/RC WALL PADANNA SIDE |
100% |
6% |
94% |
5% |
5.00% |
5.00% |
10.00% |
10.00% |
|
Raft reinforcement in progress at RHS for RC Wall |
11 |
BEAM/SLAB CHERUVATHOOR SIDE |
9 |
6 |
3 |
0 |
0 |
0 |
1 |
0 |
|
staging complete for P8-P9 and P9-P10 girder |
12 |
BEAM/SLAB PADANNA SIDE |
8 |
6 |
2 |
0.5 |
0.5 |
0.5 |
0 |
0.5 |
|
AP1-P1 Girder complete |
13 |
EXPANSION JOINT CHERUVATHUR SIDE |
9 |
3 |
6 |
1 |
1 |
0 |
1 |
2 |
|
|
14 |
EXPANSION JOINT PADANNA SIDE |
8 |
0 |
8 |
0 |
0 |
0 |
0 |
0 |
|
|
15 |
KERB CHERUVATHOOR SIDE |
100% |
22.50% |
78% |
0 |
15.00% |
25.00% |
0.00% |
15.00% |
|
P14-P13,P13-P12 span kerb complete,RC Wall kerb complete |
16 |
KERB PADANNA SIDE |
100% |
0 |
100% |
0 |
0.00% |
0.00% |
0.00% |
0.00% |
|
|
17 |
HANDRAIL CHERUVATHUR SIDE |
100% |
0% |
100% |
0 |
7.50% |
15.00% |
0.00% |
15.00% |
|
P15-P14,AP2-P15 span complete |
18 |
HANDRAIL PADANNA SIDE |
100% |
0 |
100% |
0 |
0.00% |
0.00% |
0.00% |
0.00% |
|
|
17 |
BC/PAINTING |
100% |
0 |
100% |
0 |
0.00% |
0.00% |
0.00% |
0.00% |
|
|
16 |
Deck Slab |
|
|
|
|
|
|
|
|
|
|
17 |
Utility shifting |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
Availbility of Men |
|
|
|
|
|
|
|
|
|
|
|
Date |
19-05-2012 |
20-05-2012 |
21-05-2012 |
22-05-2012 |
23-05-2012 |
24-05-2012 |
25-05-2012 |
|
|
|
|
No of labours |
74 |
66 |
69 |
69 |
69 |
12 |
69 |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
Material Stocking Status |
Required |
Available |
Remarks |
|
|
|
|
|
|
|
|
Coarse Aggreagate (m3) |
available |
|
|
|
|
|
|
|
|
|
Fine Aggreagate(m3) |
available |
|
|
|
|
|
|
|
|
|
Cement(bag) |
750 |
1300 |
|
|
|
|
|
|
|
|
|
Steel(MT) |
10 |
20 |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
Utility shifting |
|
|
|
|
|
|
|
|
|
|
|
Utilities to be shifted |
Status |
Remarks |
|
|
|
|
|
|
|
|
|
BSNL |
work to be started immediately at padanna side approach portion.AP1-P1 Location cleared for deck slab. |
|
|
|
|
|
|
|
KSEB |
in progress |
electric post infront of unity hospital need to be shifted urgently. |
|
|
|
|
|
|
|
KWA |
currently can be managed at site |
|
|
|
|
|
|
|
|
|
|
Others |
|
|
|
|
|
|
|
|
|
|