RAILWAY PORTION
Total scope: 4 Locations
LOCATIONS:P1,P7 ,P8,P2
P1,P7 –N.H side
P8,P2-Pulikkakadavu side.
Total Piles: 18
No of PILES IN EACH LOCATION
P1 location: 4
P7 location:5
P8 location:5
P2 location:4
WORK COMPLETED IN EACH LOCATION OF RAILWAY PORTION
P1 location:Piling completed (4 piles),pile cap,trestle column,trestle beam.
P7 location:5 pile concreting completed,pile cap,trestle column,trestle beam
P8 location:Piling completed(5 piles),pile cap,Trestle column,trestle beam
P2 location:Piling completed(4 piles),pile cap,trestle column,trestle beam.
Approach portion at N.H side completed 40%
WORK COMPLETED AT PULIKKAKADAVU SIDE
All deck slab concreting completed at pulikkakadavu side.
Works completed upto the roadworks,miscellaneous works, in the approach portion at pulikkakadavu side.
WORKS BALANCE
P1-P7 superstructure (RCC structure)
P7-P8 superstructure( CENTRAL SPAN)
P8-P2 superstructure (RCC structure)
Awaiting the sanction from the railways for the superstructure drawing.
WORK COMPLETED THIS WEEK
1.RE block laying in progress along with backfilling of soil in the abutment portion at NH side,compaction of soil upto the height of piercap P1
2.ISMB girder placed over the staging at P2-P8
LABOUR REPORT
DATE
|
NO: OF LABOURS
|
12-05-2012
|
9
|
14-5-2012
|
10
|
15-5-2012
|
9
|
16-5-2012
|
8
|
17-5-2012
|
10
|
18-5-2012
|
10
|
|
|
|