   weekly progress report as on 18 / 05 /2012
    

RAILWAY PORTION

Total scope: 4 Locations

 

 

LOCATIONS:P1,P7  ,P8,P2

P1,P7 –N.H side

P8,P2-Pulikkakadavu side.

Total Piles: 18

 

No of PILES IN EACH LOCATION

P1 location: 4

P7 location:5

P8 location:5

P2 location:4

 

WORK COMPLETED IN EACH LOCATION OF RAILWAY PORTION

P1 location:Piling completed (4 piles),pile cap,trestle column,trestle beam.

P7 location:5 pile concreting completed,pile cap,trestle column,trestle beam

 

P8 location:Piling completed(5 piles),pile cap,Trestle column,trestle beam

P2 location:Piling completed(4 piles),pile cap,trestle column,trestle beam.

 

Approach portion at N.H side completed 40%

 

WORK COMPLETED AT PULIKKAKADAVU SIDE

All deck slab concreting completed at pulikkakadavu side.

Works completed upto the roadworks,miscellaneous works, in the approach portion at pulikkakadavu side.

WORKS BALANCE

P1-P7 superstructure (RCC structure)

P7-P8 superstructure( CENTRAL SPAN)

P8-P2 superstructure (RCC structure)

 

 

Awaiting the sanction from the railways for the superstructure drawing.

WORK COMPLETED THIS WEEK

1.RE block laying in progress along with backfilling of soil in the abutment portion at NH side,compaction of soil upto the height of piercap P1

2.ISMB girder placed over the staging at P2-P8

 

 

 

 

 

LABOUR REPORT

DATE

NO: OF LABOURS

12-05-2012

9

14-5-2012

10

15-5-2012

9

16-5-2012

8

17-5-2012

10

18-5-2012

10

 

 

 

 

 

 

 

             

 

 

 
Back
 
    
PLACING OF ISMB GIRDERS OVER STAGING IN P2-P8 SPAN

    
    
COMPACTION WORK NEARING COMPLETION

      
 

 

 

 

 

 

 

 