Prevoius Weekly Reports

   Weekly progress report as on 18.05.2012
    
Sl.No Activity Description Total Quantity Cumulative Progress upto last week Balance work up to last week Cumulative delay in Qty up to last week Work planned during the week Actual work done during the week Cumulative delay in Qty up to this week Work planned for the next week
1 Piles 63 63 - - - - - -
2 Pile cap 21 21 - - - - - -
3 Pier  21 21 - - - - - -
4 PierCap 21 14 7 - 1 0 1 1
5 Deck Slab 21 4 17 - 1 1 0 1
6 RC wall - Kuttipuram side 100% 19% 81% - 5% 5% 0% 3%
                   
Date 12.05.12 14.05.12 15.05.12 16.05.12 17.05.12 18.05.12      
Climate Pleasant Pleasant Pleasant Pleasant Pleasant Pleasant      
No. of labours 57 57 57 57 57 57      
                   
                   
Availability of Materials                
                   
Material Required Available              
Fine aggregate 20 m3 25m3              
Coarse Aggregate 42 m3 45 m3              
Cement 220bags 280bags              
Steel 55 MT 58MT              
 
Back
 
    
RCC WALL RAFT REINFORCEMENT IN KUTTIPURAM SIDE

    
    
RCC WALL RAFT REINFORCEMENT IN KUTTIPURAM SIDE.

    
    
RCC WALL RAFT REINFORCEMENT IN KUTTIPURAM SIDE..

    
    
GIRDER AND SLAB REINFORCEMENT IN P1-P2

    
 
    
GIRDER AND SLAB REINFORCEMENT IN P1-P2.

    
    
GIRDER AND SLAB REINFORCEMENT IN P1-P2..

      
 

 

 

 

 

 

 

 