Untitled Document
Road to Prosperity
Site last updated on:  12-12-2020 | You are visitor: 7888071
Completed Projects Projects Under Construction Citizen Services Careers Right to Service


Prevoius Weekly Reports

   Weekly progress Report as on 18.05.12
    
  Description Completed/ Progress Remarks
IV ROB at Parappanangady    
  Pier cap (Total no of pier Cap- 21) Completed 21 NOS COMPLETED
  RE Wall panel casting ( total600 nos) Completed Errection completed.
  Slab calicut side  (total 10 nos ) In progress 9nos done  (adjacent span pending )
  slab NH side ( 11 nos) In progress 10nos done  (adjacent span pending )
  Retaining wall NH side completed completed
  Retaining wall calicut side completed  completed
  Dirt wall AP2 concreting  completed Done 100%
  Dirt wall AP1 concreting  completed Done 100%
  Handrail casting completed 1400 nos completed.
  Handrail fixing completed NH side 10 slab completed.Approach portion completed.
  Handrail fixing completed CALICUT side 9  span over.Approach portion completed.
  Pilling work RLY PORTION Completed PILING COMPLETED
  Pile cap RP1 Completed pier completed.
  Pile cap RP2 Completed pier completed.
  Pile cap RP3 Completed Completed
  Pile cap RP4 In progress Reinforcement work completed.
  NH side RE panel erection completed 100% completed.
  RE wall work calicut side. completed 100% completed.
  expansion joint  completed completed.
  painting-slab In progress 95% completed.
 
Back

No images are uploaded for this Weekly Reports

 
 
 

 

 

 

 

 

 

 

Untitled Document