Sl No |
Activity Description |
Total Quantity |
Cumulative progress upto last week |
Balance work up to last week |
Cumulative delay in Qty up to last week |
Work planned during the week |
Actual work done during the week |
Cumulative delay in Qty up to this week |
Work Planned for next week |
No of days remaing for completion as per the weekly plan |
Remarks |
1 |
PILE CHERUVATHOOR SIDE |
27 |
27 |
Completed |
|
|
2 |
PILE PADANNA SIDE |
24 |
24 |
Completed |
|
Piling works completed. |
3 |
PILE CAP CHERUVATHOOR SIDE |
9 |
9 |
Completed |
|
|
4 |
PILE CAP PADANNA SIDE |
8 |
8 |
Completed |
|
|
5 |
PIER CHERUVATHOOR SIDE |
9 |
9 |
Completed |
|
|
6 |
PIER PADANNA SIDE |
8 |
8 |
Completed |
|
|
7 |
PIER CAP CHERUVATHOOR SIDE |
9 |
9 |
Completed |
|
|
8 |
PIER CAP PADANNA SIDE |
8 |
8 |
Completed |
|
|
9 |
RE/RC WALL CHERUVATHOOR SIDE |
100% |
70% |
30% |
20% |
10.00% |
5.00% |
15.00% |
10.00% |
|
RE Panel fourth layer in progress,RC Wall 90% complete. |
10 |
RE/RC WALL PADANNA SIDE |
100% |
5% |
95% |
5% |
5.00% |
1.00% |
4.00% |
5.00% |
|
Excavation started for RC Wall |
11 |
BEAM/SLAB CHERUVATHOOR SIDE |
9 |
5.5 |
3.5 |
0.5 |
0.5 |
0.5 |
0 |
0 |
|
P12-P11 deck slab complete |
12 |
BEAM/SLAB PADANNA SIDE |
8 |
6 |
2 |
0 |
0.5 |
0 |
0.5 |
0.5 |
|
shuttering IP for AP1-P1 Girder |
13 |
EXPANSION JOINT CHERUVATHUR SIDE |
9 |
3 |
6 |
0 |
1 |
0 |
1 |
1 |
|
|
14 |
EXPANSION JOINT PADANNA SIDE |
8 |
0 |
8 |
0 |
0 |
0 |
0 |
0 |
|
|
15 |
KERB CHERUVATHOOR SIDE |
100% |
7.50% |
93% |
0 |
15.00% |
15.00% |
0.00% |
15.00% |
|
AP2-P15 span kerb complete,Approach portion 13 m kerb complete at RHS |
16 |
KERB PADANNA SIDE |
100% |
0 |
100% |
0 |
0.00% |
0.00% |
0.00% |
0.00% |
|
|
17 |
HANDRAIL CHERUVATHUR SIDE |
100% |
0 |
100% |
0 |
5.00% |
0.00% |
5.00% |
7.50% |
|
P15-P14 span handrail works IP |
18 |
HANDRAIL PADANNA SIDE |
100% |
0 |
100% |
0 |
0.00% |
0.00% |
0.00% |
0.00% |
|
|
17 |
BC/PAINTING |
100% |
0 |
100% |
0 |
0.00% |
0.00% |
0.00% |
0.00% |
|
|
16 |
Deck Slab |
|
|
|
|
|
|
|
|
|
|
17 |
Utility shifting |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
Availbility of Men |
|
|
|
|
|
|
|
|
|
|
|
Date |
12-05-2012 |
13-05-2012 |
14-05-2012 |
15-05-2012 |
16-05-2012 |
17-05-2012 |
18-05-2012 |
|
|
|
|
No of labours |
65 |
59 |
68 |
67 |
67 |
67 |
68 |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
Material Stocking Status |
Required |
Available |
Remarks |
|
|
|
|
|
|
|
|
Coarse Aggreagate (m3) |
available |
|
|
|
|
|
|
|
|
|
Fine Aggreagate(m3) |
available |
|
|
|
|
|
|
|
|
|
Cement(bag) |
450 |
1000 |
|
|
|
|
|
|
|
|
|
Steel(MT) |
8 |
20 |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
Utility shifting |
|
|
|
|
|
|
|
|
|
|
|
Utilities to be shifted |
Status |
Remarks |
|
|
|
|
|
|
|
|
|
BSNL |
work to be started immediately at padanna side approach portion.AP1-P1 Location cleared for deck slab. |
|
|
|
|
|
|
|
KSEB |
in progress |
electric post infront of unity hospital need to be shifted urgently. |
|
|
|
|
|
|
|
KWA |
currently can be managed at site |
|
|
|
|
|
|
|
|
|
|
Others |
|
|
|
|
|
|
|
|
|
|