Untitled Document
Road to Prosperity
Site last updated on:  12-12-2020 | You are visitor: 8052790
Completed Projects Projects Under Construction Citizen Services Careers Right to Service


Prevoius Weekly Reports

   Weekly progress report as on 18.05.2012
    
Sl No  Activity Description  Total Quantity Cumulative progress upto last week  Balance  work up to last week Cumulative delay in Qty up to last week Work  planned  during the week  Actual work done during the week  Cumulative delay in Qty up to this week Work  Planned for next week  No of days remaing for completion as per the weekly plan Remarks 
1 PILE CHERUVATHOOR  SIDE 27 27 Completed    
2 PILE PADANNA SIDE 24 24 Completed   Piling works completed.
3 PILE CAP CHERUVATHOOR SIDE 9 9 Completed    
4 PILE CAP  PADANNA SIDE 8 8 Completed    
5 PIER CHERUVATHOOR SIDE 9 9 Completed    
6 PIER PADANNA SIDE 8 8 Completed    
7 PIER CAP CHERUVATHOOR SIDE 9 9 Completed    
8 PIER CAP PADANNA SIDE 8 8 Completed    
9 RE/RC WALL CHERUVATHOOR  SIDE 100% 70% 30% 20% 10.00% 5.00% 15.00% 10.00%   RE Panel fourth layer in progress,RC Wall 90% complete.
10 RE/RC  WALL PADANNA SIDE 100% 5% 95% 5% 5.00% 1.00% 4.00% 5.00%   Excavation started for RC Wall
11 BEAM/SLAB CHERUVATHOOR  SIDE 9 5.5 3.5 0.5 0.5 0.5 0 0   P12-P11 deck slab complete
12 BEAM/SLAB PADANNA SIDE 8 6 2 0 0.5 0 0.5 0.5   shuttering IP for AP1-P1 Girder
13 EXPANSION JOINT CHERUVATHUR SIDE 9 3 6 0 1 0 1 1    
14 EXPANSION JOINT PADANNA SIDE 8 0 8 0 0 0 0 0    
15 KERB CHERUVATHOOR  SIDE 100% 7.50% 93% 0 15.00% 15.00% 0.00% 15.00%   AP2-P15 span kerb complete,Approach portion 13 m kerb complete at RHS
16 KERB PADANNA SIDE 100% 0 100% 0 0.00% 0.00% 0.00% 0.00%    
17 HANDRAIL CHERUVATHUR SIDE 100% 0 100% 0 5.00% 0.00% 5.00% 7.50%   P15-P14 span handrail works IP
18 HANDRAIL PADANNA SIDE 100% 0 100% 0 0.00% 0.00% 0.00% 0.00%    
17 BC/PAINTING 100% 0 100% 0 0.00% 0.00% 0.00% 0.00%    
16 Deck Slab                    
17 Utility shifting                    
                       
                       
                       
  Availbility of Men                     
  Date 12-05-2012 13-05-2012 14-05-2012 15-05-2012 16-05-2012 17-05-2012 18-05-2012      
  No of labours 65 59 68 67 67 67 68      
                       
  Material Stocking Status Required Available Remarks              
  Coarse Aggreagate (m3) available                
  Fine Aggreagate(m3) available                
  Cement(bag) 450 1000                
  Steel(MT) 8 20              
                       
                       
  Utility shifting                    
  Utilities to be shifted Status Remarks                
  BSNL work to be started immediately at padanna side approach portion.AP1-P1 Location cleared for deck slab.            
  KSEB in progress electric post infront of unity hospital need to be shifted urgently.            
  KWA currently can be managed at site                   
  Others                    
 
Back
 
    
SHUTTERING IP FOR AP1-P1 GIRDER

    
    
P12-P11 DECK SLAB CONCRETE

    
    
KERB SHUTTERING IP

    
    
HANDRAIL WORKS IP FOR P15-P14 SPAN

    
 
    
EXCAVATION IN SLOW PHASE AT PADANNA SIDE FOR RC WALL

    
    
CHR SIDE RE PANEL WORKS IP

    
    
CHR SIDE APPROACH KERB WORKS IP

    
 
    
AP1-P1 GIRDER REINF IP

      
 

 

 

 

 

 

 

 

Untitled Document