   Weekly progress report as on 18.05.2012
    
Si No  Activity Description  Total Quantity Cumulative progress upto 17.05.12 Balance  work up to 17.05.12 Cumulative delay in Qty up to 17.05.12 Work  planned  during the week  Actual work done during the week delay in Qty up to this week Work  Planned for next week  No of days remaing for completion as per the weekly plan Remarks 
1 PILE  Palarivattom side(Approach portion) 31 31 0 0 2 2 0 0   KWA line to be shifted. Will be over by 18.01.12. work completed on 23.01.12.Rig erected at P9
2 PILE Palarivattom side(railway portion) 6 5 1 0 1 0 1 1
3 PILE vytilla side(Approach portion) 42 42 0 0 0 0 0 0   Pipe line broken on 26.01.12 at 2.20 am while boring.Repaired on 26.01.12
4 PILE vytilla side(railway portion) 6 5 1 0 0 0 0 1   RP1 P4 done . RP1 P5 was abandoned due to pile choking. Pile layout to be redesigned.Piling resumed on 29.02.12. Piling held up pending approval  fron RLY
5 PILE CAP Palarivattom side(Approach portion) 8 8 0 0 0 0 0 0   KWA line to be shifted. Will be over by 18.01.12. work completed on 23.01.12.
6 PILE CAP Palarivattom side(railway portion) 1 0 1 0 0 0 0 0
7 PILE CAP vytilla side(Approach portion) 9 9 0 0 0 0 0 0   P1,  P2, P4, P3, A1, P5,P6, P7,P8
8 PILE CAP vytilla side(railway portion) 1 0 1 0 0 0 0 0    
9 PIER Palarivattom side(Approach portion) 8 7 1 0 1 0 1 1   A2, P15, P14, P13,  P12,  P11, P10 
10 PIER Palarivattomside(railway portion) 1 0 1 0 0 0 0 0    
11 PIER Vytilla side(Approach portion) 9 8 1 0 2 0 2 2 "      " P1, P2, P3, P4, A1,P5,P6,P7
12 PIER vytilla side(railway portion) 1 0 1 0 0 0 0 0 "      "  
13 PIER  CAP Palarivattom side(Approach portion) 8 7 1 0 0 0 0 0   P15, P14, A2, P13, P12, P11, P10
14 PIER  CAP Vytila side(Approach portion) 9 6 3 1 1 0 0 1   P1, P2, P3, A1,P4,P5
15 GIRDER Palarivattom side(Approach portion) 7 6 1 0 0 0 0 0   A2 P15,P15 P14,P14 P13, P13 P12, P11 P10, P12 P11
16 GIRDERVytila side(Approach portion) 9 2 7 0 0 0 0 0   P1 P2,  A1P1
17 DECK SLAB Palarivattom side(Approach portion) 7 6 1 0 1 0 1 0   A2 P15, P15 P14, P14 P13,  P13 P12, P11P10, P12 P11
18 DECK SLABVytila side(Approach portion) 9 1 8 0 0 0 0 1   P1P2
19 PIER CAP Palarivattomside(railway portion) 1 0 1 0 0 0 0 0    
20 PIER CAP vytilla side(railway portion) 1 0 1 0 0 0 0 0    
21 RE WALL PANEL 351 351 0 0 0 0 0 0    
20 RE WALL PCC Palarivattom 95 95 0 0 0 0 0 0   Rerouting of water connection to photostat shop  by KWA to the completed on 24.03.12. on 24.04.12 the entire RE Wall area was cleared for excavation.
21 RE WALL Panel erection Palarivattom 100% 15% 0.85 0 60% 0 0 0   Rerouting of water connection to photostat shop  by KWA to the completed on 24.03.12. on 24.04.12 the entire RE Wall area was cleared for excavation.Panel erection commenced on 15.05.12
                       
                       
                   
                     
                       
  Labour Report                    
                       
  Date 11.05.12 12.05.12 13.05.12 14.05.12 15.05.12 16.05.12 17.05.12      
  Day Fri Sat Sun Mon Tue Wed Thurs      
  Climate sunny  sunny  sunny  sunny sunny  sunny   sunny      
  No.of labours 49 51 43 61 50 62 61      
  Remarks     no piling Sunday   no piling  due to pipe line(discarded) beneath.       
                       
  Availability of Material                     
                       
  Materials Required for week ending on 24.05.12 Available as on 18.05.12                
  Fine aggregate(M3) Ready Mix Concrete                
  Coarse aggregate(M3)                
  Cement(BAG)                
  Steel(TONN) 9 42                
 
Back
 
    
SIDE SHUTTERING P2P3

    
    
RE WALL WORKS PLRVTM

    
    
PROFILING P2P3

    
    
PIER CAP P6

    
 
    
P8 PIER

    
    
GIRDER P2P3

      
 

 

 

 

 

 

 

 