   Weekly progress report as on 11.05.2012
    
Sl.No Activity Description Total Quantity Cumulative Progress upto last week Balance work up to last week Cumulative delay in Qty up to last week Work planned during the week Actual work done during the week Cumulative delay in Qty up to this week Work planned for the next week
1 Piles 63 63 - - - - - -
2 Pile cap 21 21 - - - - - -
3 Pier  21 21 - - - - - -
4 PierCap 21 14 7 - 1 0 1 1
5 Deck Slab 21 3 18 - 1 1 1 1
6 RC wall - Kuttipuram side 100% 16% 84% - 5% 1% 4% 2%
                   
Date 05.05.12 07.05.12 08.05.12 09.05.12 10.05.12 11.05.12      
Climate Pleasant Pleasant Pleasant Pleasant Pleasant Pleasant      
No. of labours 57 57 57 57 57 57      
                   
                   
Availability of Materials                  
                   
Material Required Available              
Fine aggregate 45 m3 25m3              
Coarse Aggregate 90 m3 45 m3              
Cement 850bags 400bags              
Steel 35 MT 35MT              
 