   Weekly progress report as on 11.05.2012
    
Sl No  Activity Description  Total Quantity Cumulative progress upto last week  Balance  work up to last week Cumulative delay in Qty up to last week Work  planned  during the week  Actual work done during the week  Cumulative delay in Qty up to this week Work  Planned for next week  No of days remaing for completion as per the weekly plan Remarks 
1 PILE CHERUVATHOOR  SIDE 27 27 Completed    
2 PILE PADANNA SIDE 24 24 Completed   Piling works completed.
3 PILE CAP CHERUVATHOOR SIDE 9 9 Completed    
4 PILE CAP  PADANNA SIDE 8 8 Completed    
5 PIER CHERUVATHOOR SIDE 9 9 Completed    
6 PIER PADANNA SIDE 8 8 Completed    
7 PIER CAP CHERUVATHOOR SIDE 9 9 Completed    
8 PIER CAP PADANNA SIDE 8 8 Completed    
9 RE/RC WALL CHERUVATHOOR  SIDE 100% 65% 35% 20% 20.00% 5.00% 20.00% 10.00%   RE Panel fourth layer in progress,RC Wall 90% complete.
10 RE/RC  WALL PADANNA SIDE 100% 0 100% 5% 5.00% 5.00% 5.00% 5.00%   Excavation started for RC Wall
11 BEAM/SLAB CHERUVATHOOR  SIDE 9 5 4 0 1 0.5 0.5 0.5   P12-P11 girder complete
12 BEAM/SLAB PADANNA SIDE 8 6 2 0 0 0 0 0.5   staging started at AP1-P1 Location
13 EXPANSION JOINT CHERUVATHUR SIDE 9 2 9 0 1 1 0 1   P13 location
14 EXPANSION JOINT PADANNA SIDE 8 0 8 0 0 0 0 0    
15 KERB CHERUVATHOOR  SIDE 100% 0 100% 0 7.50% 7.50% 0.00% 15.00%   P15-P14 span kerb complete
16 KERB PADANNA SIDE 100% 0 100% 0 0.00% 0.00% 0.00% 0.00%    
17 HANDRAIL CHERUVATHUR SIDE 100% 0 100% 0 0.00% 0.00% 0.00% 5.00%   Handrail horizontal casting IP
18 HANDRAIL PADANNA SIDE 100% 0 100% 0 0.00% 0.00% 0.00% 0.00%    
17 BC/PAINTING 100% 0 100% 0 0.00% 0.00% 0.00% 0.00%    
16 Deck Slab                    
17 Utility shifting                    
                       
                       
                       
  Availbility of Men                     
  Date 05-04-2012 06-04-2012 07-04-2012 08-05-2012 09-05-2012 10-05-2012 11-05-2012      
  No of labours 66 48 67 68 68 67 68      
                       
  Material Stocking Status Required Available Remarks              
  Coarse Aggreagate (m3) available                
  Fine Aggreagate(m3) available                
  Cement(bag) 450 400 shortage              
  Steel(MT) 10 25              
                       
                       
  Utility shifting                    
  Utilities to be shifted Status Remarks                
  BSNL work to be started immediately at padanna side approach portion.AP1-P1 Location cleared for deck slab.            
  KSEB in progress electric post infront of unity hospital need to be shifted urgently.            
  KWA currently can be managed at site                   
  Others                    
 
Back
 
    
P15-P14 KERB CONCRETE IN PROGRESS

    
    
STAGING COMPLETE FOR P8-P9 GIRDER

    
    
RE PANEL WORK IP

    
    
P12-P11 GIRDER COMPLETE

    
 
 
 

 

 

 

 

 

 

 