   Weekly progress report as on 11.05.2012
    
Si No  Activity Description  Total Quantity Cumulative progress upto last week  Balance  work up to last week Cumulative delay in Qty up to last week Work  planned  during the week  Actual work done during the week  Cumulative delay in Qty up to this week Work  Planned for next week  No of days remaining for completion as per the weekly plan Remarks 
1 PILE Muthambi side 27 26 2 0 1 0 1 1 3  
2 PILE Thamarassery side 33 33 0 0 0 0 0 0    
3 PILE NH SIDE 30 30 0 0 0 0 0 0    
4 PILE CAP Muthambi SIDE 9 6 3 0 1 0 1 1 5 Work in progress.
5 PILE CAP Thamarassery SIDE 11 10 1 0 1 0 1 1 7  
6 PILE CAP NH SIDE 10 9 0 0 0 0 0 0    
7 PIER Muthambi  SIDE 9 6 3 0 0 0 0 0    
8 PIER Thamarassery SIDE 11 10 1 0 0 0 0 0    
9 PIER NH SIDE 10 9 1 0 0 0 0 0    
10 PIER CAP Muthambi  SIDE 9 6 0 0 0 0 0 0    
11 PIER CAP Thamarassery SIDE 11 9 2 0 1 0 1 1 3 steel work in final stage
12 PIER CAP NH SIDE 10 7 2 0 2 2 0 0    
13 RE/R WALL Muthambi side 100% 0 100% 0 0.00% 0.00% 0 0.00%    
14 RE/R WALL Thamarassery side SIDE 100% 5% 95% 0 10.00% 5.00% 0.05 10.00% Site clearance & excavation completed.PCC done at one side  
15 RE/R WALL NH SIDE 100% 35% 65% 0 25.00% 0.00% 0.25 25.00% Raft COMPLETED.Shuttering work in progress  
16 BEAM/SLAB Muthambi SIDE 8 5 3 0 0 0 0 0    
17 BEAM/SLAB Thamarassery SIDE 10 3 7 0 1 0 1 2 shuttering work between P25-P24 & P27-AP3 for girder in progress  
18 BEAM/SLAB NH SIDE 11 6 5 0 0 0 0 0    
19 HR/FP/KERB Muthambi SIDE 100% 0 100% 0 0.00% 0.00% 0 0.00%    
20 HR/FP/KERB thamarassery SIDE 100% 0 100% 0 0.00% 0.00% 0 0.00%    
21 HR/FP/KERB NH SIDE 100% 0 100% 0 0.00% 0.00% 0 0.00%    
22 BC/PAINTING 100% 0 100% 0 0.00% 0.00% 0 0.00%    
23 Utility shifting             0     KSEB utility shifting started. Shifted 1 post
                       
                       
                       
  Availbility of Men                     
  Date 05-05-2012 05-06-2012 05-07-2012 05-08-2012 05-09-2012 05-10-2012 05-11-2012      
  Nof labours 55 40 55 60 62 62 62      
                       
  Material Stocking Status Required Available Remarks              
  Coarse Aggreagate (m3) 50 60                
  Fine Aggreagate(m3) 50 60                
  Cement(bag) 1000 1700                
  Steel(MT) 40 70                
                       
                       
  Utility shifting                    
  Utilities to be shifted Status Remarks                
  BSNL                    
  KSEB                    
  KWA                    
  Others                    
                       
 
Back
 
    
STAGING IN PROGRESS P21-P22

    
    
RETAINING WALL WORK IN PROGRESS AT AP3

    
    
PIER CAP CONCRETING DONE AT P7&P8

      
 

 

 

 

 

 

 

 