Prevoius Weekly Reports

   Weekly progress report as on 11.05.2012
    
Si No  Activity Description  Total Quantity Cumulative progress upto 10.05.12 Balance  work up to 10.05.12 Cumulative delay in Qty up to 10.05.12 Work  planned  during the week  Actual work done during the week delay in Qty up to this week Work  Planned for next week  No of days remaing for completion as per the weekly plan Remarks 
1 PILE  Palarivattom side(Approach portion) 31 31 0 0 2 2 0 0   KWA line to be shifted. Will be over by 18.01.12. work completed on 23.01.12.Rig erected at P9
2 PILE Palarivattom side(railway portion) 6 5 1 0 1 0 1 1
3 PILE vytilla side(Approach portion) 42 42 0 0 0 0 0 0   Pipe line broken on 26.01.12 at 2.20 am while boring.Repaired on 26.01.12
4 PILE vytilla side(railway portion) 6 5 1 0 0 0 0 1   RP1 P4 done . RP1 P5 was abandoned due to pile choking. Pile layout to be redesigned.Piling resumed on 29.02.12. Piling held up pending approval  fron RLY
5 PILE CAP Palarivattom side(Approach portion) 8 8 0 0 0 0 0 0   KWA line to be shifted. Will be over by 18.01.12. work completed on 23.01.12.
6 PILE CAP Palarivattom side(railway portion) 1 0 1 0 0 0 0 0
7 PILE CAP vytilla side(Approach portion) 9 9 0 0 0 0 0 0   P1,  P2, P4, P3, A1, P5,P6, P7,P8
8 PILE CAP vytilla side(railway portion) 1 0 1 0 0 0 0 0    
9 PIER Palarivattom side(Approach portion) 8 7 1 0 1 0 1 1   A2, P15, P14, P13,  P12,  P11, P10 
10 PIER Palarivattomside(railway portion) 1 0 1 0 0 0 0 0    
11 PIER Vytilla side(Approach portion) 9 7 2 0 2 0 2 2 "      " P1, P2, P3, P4, A1,P5,P6
12 PIER vytilla side(railway portion) 1 0 1 0 0 0 0 0 "      "  
13 PIER  CAP Palarivattom side(Approach portion) 8 7 1 0 0 0 0 0   P15, P14, A2, P13, P12, P11, P10
14 PIER  CAP Vytila side(Approach portion) 9 5 4 1 1 0 0 1   P1, P2, P3, A1,P4
15 GIRDER Palarivattom side(Approach portion) 7 6 1 0 0 0 0 0   A2 P15,P15 P14,P14 P13, P13 P12, P11 P10, P12 P11
16 GIRDERVytila side(Approach portion) 9 2 7 0 0 0 0 0   P1 P2,  A1P1
17 DECK SLAB Palarivattom side(Approach portion) 7 6 1 0 1 0 1 0   A2 P15, P15 P14, P14 P13,  P13 P12, P11P10, P12 P11
18 DECK SLABVytila side(Approach portion) 9 1 8 0 0 0 0 1   P1P2
19 PIER CAP Palarivattomside(railway portion) 1 0 1 0 0 0 0 0    
20 PIER CAP vytilla side(railway portion) 1 0 1 0 0 0 0 0    
21 RE WALL PANEL 351 351 0 0 0 0 0 0    
20

RE WALL PCC Palarivattom

 

95 87 8 0 0 0 0 0   Rerouting of water connection to photostat shop  by KWA to the completed on 24.03.12. on 24.04.12 the entire RE Wall area was cleared for excavation.

 

 

  Labour Report                  
                     
  Date 04.05.12 05.05.12 06.05.12 07.05.12 08.05.12 09.05.12 10.05.12    
  Day Fri Sat Sun Mon Tue Wed Thurs    
  Climate sunny  sunny  sunny  sunny sunny  sunny   sunny    
  No.of labours 63 16 34 59.5 67 59 56    
  Remarks   harthal no piling Sunday            
                     
  Availability of Material                   
                     
  Materials Required for week ending on 17.05.12 Available as on 11.05.12              
  Fine aggregate(M3) Ready Mix Concrete              
  Coarse aggregate(M3)              
  Cement(BAG)              
  Steel(TONN) 8 42              
 
Back
 
    
STRESSING A1 P1

    
    
RE WALL PCC PALARIVATTOM SIDE

    
    
PEDESTAL CONCRETING P4

      
 

 

 

 

 

 

 

 