   Weekly progress report as on 11.05.2012
    

PROGRESS REPORT (upto May 11th 2012)

RAILWAY PORTION

Total scope: 4 Locations

 

 

LOCATIONS:P1,P7  ,P8,P2

P1,P7 –N.H side

P8,P2-Pulikkakadavu side.

Total Piles: 18

 

No of PILES IN EACH LOCATION

P1 location: 4

P7 location:5

P8 location:5

P2 location:4

 

WORK COMPLETED IN EACH LOCATION OF RAILWAY PORTION

P1 location:Piling completed (4 piles),pile cap,trestle column,trestle beam.

P7 location:5 pile concreting completed,pile cap,trestle column,trestle beam

 

P8 location:Piling completed(5 piles),pile cap,Trestle column,trestle beam

P2 location:Piling completed(4 piles),pile cap,trestle column,trestle beam.

 

Approach portion at N.H side completed 40%

 

WORK COMPLETED AT PULIKKAKADAVU SIDE

All deck slab concreting completed at pulikkakadavu side.

Works completed upto the roadworks,miscellaneous works, in the approach portion at pulikkakadavu side.

WORKS BALANCE

P1-P7 superstructure (RCC structure)

P7-P8 superstructure( CENTRAL SPAN)

P8-P2 superstructure (RCC structure)

 

 

Awaiting the sanction from the railways for the superstructure drawing.

WORK COMPLETED THIS WEEK

1.RE block laying in progress along with backfilling of soil in the abutment portion at NH side.

2.ISMB girder placed over the staging at P2-P8

 

 

 

 

 

LABOUR REPORT

DATE

NO: OF LABOURS

05-05-2012

11

07-5-2012

10

08-5-2012

12

09-5-2012

12

10-5-2012

11

11-5-2012

12

 

 

 

 

 
Back
 
    
SOIL AFTER LEVELLING AT N.H SIDE

    
    
LEVELLING AND SPREADING OF THE SOIL IN RE WALL PORTION

    
    
COMPACTION OF SOIL IN RE WALL AT N.H SIDE

      
 

 

 

 

 

 

 

 