   Weekly progress Report as on 04.05.12
    
Si No  Activity Description  Total Quantity Cumulative progress upto last week  Balance  work up to last week Cumulative delay in Qty up to last week Work  planned  during the week  Actual work done during the week  Cumulative delay in Qty up to this week Work  Planned for next week  No of days remaing for completion as per the weekly plan Remarks   
1 PILE KAINATTY  SIDE 18 18 0 0 0 0 0 0      
2 PILE NADAPURAM SIDE 27 27 0 0 0 0 0 0      
3 PILE CAP KAINATTY SIDE 6 6 0 0 0 0 0 0      
4 PILE CAP  NADAPURAM SIDE 9 9 0 0 0 0 0 0      
  PIER KAINATTY  SIDE 6 6 0 0 0 0 0 0      
6 PIER NADAPURAM SIDE 9 9 0 0 0 0 0 0      
7 PIER CAP KAINATTY  SIDE 6 6 0 0 0 0 0 0      
8 PIER CAP NADAPURAM SIDE 9 9 0 0 0 0 0 0      
11 RE/R WALL KAINATTY  SIDE 100% 100% nil nil 3.00% 3.00% nil nil   Painting completed.  
10 RE/R WALL NADAPURAM SIDE 100% 100% nil nil 5.00% 5.00% nil nil   Painting completed.  
12 BEAM/SLAB  Staging Kainatty side 6 5 1 1 1 1 1 0      
13 BEAM/SLAB  Bar bending and Fixing Kainatty side 6 5 1 1 1 1 1 0      
14 BEAM/SLAB  Shuttering  and Concreting  Kainatty side 6 5 1 1 1 0 1 1      
15 BEAM/SLAB  Staging Nadapuram side 9 8 1 1 0 0 1 0      
16 BEAM/SLAB  Bar bending and Fixing Nadapuram side 9 8 1 1 1 1 1 1   P6-P7 girder completed.  
17 BEAM/SLAB  Shuttering  and Concreting  Nadapuram side 9 8 1 1 1 0* 1 1   P6-P7 girder completed.  
18 BEAM/SLAB KAINATTY  SIDE 6 5 1 1 1 1 1 0      
19 BEAM/SLAB NADAPURAM SIDE 9 8 1 1 1 1 2 1      
20 HR/FP/KERB KAINATTY  SIDE 100% 100% 0% 0% 50.00% 50.00% 0.00% 0.00%      
21 HR/FP/KERB NADAPURAM SIDE 100% 100% 0% 0% 10.00% 10.00% 0.00% 0.00%      
22 BC/PAINTING 100% 98% 2% 2% 10.00% 8.00% 20.00% 2.00%      
                         
                         
  Note: Progress review done based on the revised Program (rev-01)            
                         
                         
  Availbility of Men                       
  Date   28-04-12 29-04-12 30-04-12 ######## ####### 04-03-2012 04-04-2012      
  Nof labours   12 12 12 12 10 10 10      
                         
  Material Stocking Status Required Available Remarks                
                         
  Fine Aggreagate(m3) 1 4                  
  Cement(bag) 4 15                  
  Steel(MT) nil 0.5                  
  Coarse Aggreagate (m3) 1 3                  
                         
  Utility shifting                      
  Utilities to be shifted Status Remarks                  
  BSNL shifted                    
  KSEB shifted                    
  KWA shifted                    
  Others shifted                    
 
Back
 
    
CLEANING ROAD AT KAINATTY SIDE

    
    
HUME PIPE FO DRAINAGE ALONG SERVICE ROAD

    
    
HOT MIX PLANT OPERATION

    
    
EXCAVATION FOR DRAIN ALONG SERVICE ROAD AT NADAPURAM SIDE

    
 
    
BC FIRST LAYER AT KAINATTY SIDE

      
 

 

 

 

 

 

 

 