Activity Description |
Total Quantity |
Cumulative progress upto last week |
Balance work up to last week |
Cumulative delay in Qty up to last week |
Work planned during the week |
Actual work done during the week |
Cumulative delay in Qty up to this week |
Work Planned for next week |
No of days remaining for completion as per the weekly plan |
Remarks |
PILE Muthambi side |
27 |
25 |
2 |
0 |
2 |
1 |
1 |
1 |
3 |
|
PILE Thamarassery side |
33 |
33 |
0 |
0 |
0 |
0 |
0 |
0 |
|
|
PILE NH SIDE |
30 |
30 |
0 |
0 |
0 |
0 |
0 |
0 |
|
|
PILE CAP Muthambi SIDE |
9 |
6 |
3 |
0 |
1 |
0 |
1 |
1 |
7 |
|
PILE CAP Thamarassery SIDE |
11 |
10 |
1 |
0 |
0 |
0 |
0 |
1 |
|
Work in progress. |
PILE CAP NH SIDE |
10 |
9 |
0 |
0 |
0 |
0 |
0 |
0 |
|
|
PIER Muthambi SIDE |
9 |
6 |
3 |
0 |
0 |
0 |
0 |
0 |
|
|
PIER Thamarassery SIDE |
11 |
10 |
1 |
0 |
0 |
0 |
0 |
1 |
|
|
PIER NH SIDE |
10 |
8 |
1 |
0 |
1 |
1 |
0 |
0 |
2 |
only last lift is pending |
PIER CAP Muthambi SIDE |
9 |
6 |
0 |
0 |
0 |
0 |
0 |
0 |
|
|
PIER CAP Thamarassery SIDE |
11 |
8 |
2 |
0 |
2 |
1 |
1 |
1 |
3 |
steel work in final stage |
PIER CAP NH SIDE |
10 |
7 |
2 |
0 |
0 |
0 |
0 |
2 |
|
|
RE/R WALL Muthambi side |
100% |
0 |
100% |
0 |
0.00% |
0.00% |
0 |
0.00% |
|
|
RE/R WALL Thamarassery side SIDE |
100% |
5% |
95% |
0 |
0.00% |
0.00% |
0 |
10.00% |
Site clearance & excavation completed |
|
RE/R WALL NH SIDE |
100% |
35% |
65% |
0 |
25.00% |
10.00% |
0.15 |
25.00% |
Raft COMPLETED.Shuttering work in progress |
|
BEAM/SLAB Muthambi SIDE |
8 |
5 |
3 |
0 |
0 |
0 |
0 |
0 |
|
|
BEAM/SLAB Thamarassery SIDE |
10 |
3 |
7 |
0 |
1 |
0 |
1 |
1 |
|
|
BEAM/SLAB NH SIDE |
11 |
6 |
5 |
0 |
1 |
0 |
1 |
0 |
|
|
HR/FP/KERB Muthambi SIDE |
100% |
0 |
100% |
0 |
0.00% |
0.00% |
0 |
0.00% |
|
|
HR/FP/KERB thamarassery SIDE |
100% |
0 |
100% |
0 |
0.00% |
0.00% |
0 |
0.00% |
|
|
HR/FP/KERB NH SIDE |
100% |
0 |
100% |
0 |
0.00% |
0.00% |
0 |
0.00% |
|
|
BC/PAINTING |
100% |
0 |
100% |
0 |
0.00% |
0.00% |
0 |
0.00% |
|
|
Utility shifting |
|
|
|
|
|
|
0 |
|
|
KSEB utility shifting started. Shifted 1 post |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
Availbility of Men |
|
|
|
|
|
|
|
|
|
|
Date |
28/4/2012 |
29/4/2012 |
30/4/2012 |
05-01-2012 |
05-02-2012 |
05-03-2012 |
05-04-2012 |
|
|
|
Nof labours |
51 |
42 |
48 |
52 |
49 |
52 |
50 |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
Material Stocking Status |
Required |
Available |
Remarks |
|
|
|
|
|
|
|
Coarse Aggreagate (m3) |
50 |
60 |
|
|
|
|
|
|
|
|
Fine Aggreagate(m3) |
50 |
60 |
|
|
|
|
|
|
|
|
Cement(bag) |
1000 |
1500 |
|
|
|
|
|
|
|
|
Steel(MT) |
40 |
58 |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|