Prevoius Weekly Reports

   Weekly progress report as on 04.05.2012
    
Activity Description  Total Quantity Cumulative progress upto last week  Balance  work up to last week Cumulative delay in Qty up to last week Work  planned  during the week  Actual work done during the week  Cumulative delay in Qty up to this week Work  Planned for next week  No of days remaining for completion as per the weekly plan Remarks 
PILE Muthambi side 27 25 2 0 2 1 1 1 3  
PILE Thamarassery side 33 33 0 0 0 0 0 0    
PILE NH SIDE 30 30 0 0 0 0 0 0    
PILE CAP Muthambi SIDE 9 6 3 0 1 0 1 1 7  
PILE CAP Thamarassery SIDE 11 10 1 0 0 0 0 1   Work in progress.
PILE CAP NH SIDE 10 9 0 0 0 0 0 0    
PIER Muthambi  SIDE 9 6 3 0 0 0 0 0    
PIER Thamarassery SIDE 11 10 1 0 0 0 0 1    
PIER NH SIDE 10 8 1 0 1 1 0 0 2 only last lift is pending
PIER CAP Muthambi  SIDE 9 6 0 0 0 0 0 0    
PIER CAP Thamarassery SIDE 11 8 2 0 2 1 1 1 3 steel work in final stage
PIER CAP NH SIDE 10 7 2 0 0 0 0 2    
RE/R WALL Muthambi side 100% 0 100% 0 0.00% 0.00% 0 0.00%    
RE/R WALL Thamarassery side SIDE 100% 5% 95% 0 0.00% 0.00% 0 10.00% Site clearance & excavation completed  
RE/R WALL NH SIDE 100% 35% 65% 0 25.00% 10.00% 0.15 25.00% Raft COMPLETED.Shuttering work in progress  
BEAM/SLAB Muthambi SIDE 8 5 3 0 0 0 0 0    
BEAM/SLAB Thamarassery SIDE 10 3 7 0 1 0 1 1    
BEAM/SLAB NH SIDE 11 6 5 0 1 0 1 0    
HR/FP/KERB Muthambi SIDE 100% 0 100% 0 0.00% 0.00% 0 0.00%    
HR/FP/KERB thamarassery SIDE 100% 0 100% 0 0.00% 0.00% 0 0.00%    
HR/FP/KERB NH SIDE 100% 0 100% 0 0.00% 0.00% 0 0.00%    
BC/PAINTING 100% 0 100% 0 0.00% 0.00% 0 0.00%    
Utility shifting             0     KSEB utility shifting started. Shifted 1 post
                     
                     
                     
Availbility of Men                     
Date 28/4/2012 29/4/2012 30/4/2012 05-01-2012 05-02-2012 05-03-2012 05-04-2012      
Nof labours 51 42 48 52 49 52 50      
                     
Material Stocking Status Required Available Remarks              
Coarse Aggreagate (m3) 50 60                
Fine Aggreagate(m3) 50 60                
Cement(bag) 1000 1500                
Steel(MT) 40 58                
                     
 
Back
 
    
RETAINING WALL RAFT AT NH SIDE

    
    
PIER CAP WORK IN PROGRESS AT P7

    
    
GIRDER CONCRETING P5-P6

      
 

 

 

 

 

 

 

 