Untitled Document
Road to Prosperity
Site last updated on:  12-12-2020 | You are visitor: 8053161
Completed Projects Projects Under Construction Citizen Services Careers Right to Service


Prevoius Weekly Reports

   Weekly progress report as on 04.05.2012
    
Sl No  Activity Description  Total Quantity Cumulative progress upto last week  Balance  work up to last week Cumulative delay in Qty up to last week Work  planned  during the week  Actual work done during the week  Cumulative delay in Qty up to this week Work  Planned for next week  No of days remaing for completion as per the weekly plan Remarks 
1 PILE CHERUVATHOOR  SIDE 27 27 Completed    
2 PILE PADANNA SIDE 24 24 Completed   Piling works completed.
3 PILE CAP CHERUVATHOOR SIDE 9 9 Completed    
4 PILE CAP  PADANNA SIDE 8 8 Completed    
5 PIER CHERUVATHOOR SIDE 9 9 Completed    
6 PIER PADANNA SIDE 8 8 Completed    
7 PIER CAP CHERUVATHOOR SIDE 9 9 Completed    
8 PIER CAP PADANNA SIDE 8 8 Completed    
9 RE/R WALL CHERUVATHOOR  SIDE 100% 60% 40% 20% 20.00% 5.00% 30.00% 20.00%   RE Panel third layer in progress,RC Wall 90% complete.
10 RE/R WALL PADANNA SIDE 100% 0 100% 5% 5.00% 0.00% 10.00% 5.00%    
11 BEAM/SLAB CHERUVATHOOR  SIDE 9 5 4 0 0.5 0 0.5 1   shuttering 80% complete for P12-P11 girder
12 BEAM/SLAB PADANNA SIDE 8 5.5 2.5 0 0.5 0.5 0 0   P4-P5 slab complete,AP1-P1 location bsnl cable shifting in progress.
13 EXPANSION JOINT CHERUVATHUR SIDE 9 0 9 0 3 2 1 1   P15,P14 locations
14 EXPANSION JOINT PADANNA SIDE 8 0 8 0 0 0 0 0    
15 KERB CHERUVATHOOR  SIDE 100% 0 100% 0 12.50% 0.00% 12.50% 12.50%    
16 KERB PADANNA SIDE 100% 0 100% 0 0.00% 0.00% 0.00% 0.00%    
17 HANDRAIL CHERUVATHUR SIDE 100% 0 100% 0 0.00% 0.00% 0.00% 0.00%   Handrail horizontal casting IP
18 HANDRAIL PADANNA SIDE 100% 0 100% 0 0.00% 0.00% 0.00% 0.00%    
17 BC/PAINTING 100% 0 100% 0 0.00% 0.00% 0.00% 0.00%    
16 Deck Slab                    
17 Utility shifting                    
                       
                       
                       
  Availbility of Men                     
  Date 28-04-2012 29-04-2012 30-04-2012 01-05-2012 02-05-2012 03-05-2012 04-05-2012      
  No of labours 74 64 64 46 57 68 67      
                       
  Material Stocking Status Required Available Remarks              
  Coarse Aggreagate (m3) available                
  Fine Aggreagate(m3) available                
  Cement(bag) 500 800                
  Steel(MT) 8 15              
                       
                       
  Utility shifting                    
  Utilities to be shifted Status Remarks                
  BSNL work to be started immediately at padanna side approach portion.Work in progress at AP1-P1 deck slab location.            
  KSEB in progress electric post infront of unity hospital need to be shifted urgently.            
  KWA currently can be managed at site                   
  Others                    
                       
 
Back
 
    
VIEW OF PADANNA SIDE

    
    
RE PANEL WORKS IP

    
    
P12-P11 GIRDER SHUTTERING IP

    
    
CHR SIDE-EXPANSION JOINT WORKS IP

    
 
 
 

 

 

 

 

 

 

 

Untitled Document