Sl No |
Activity Description |
Total Quantity |
Cumulative progress upto last week |
Balance work up to last week |
Cumulative delay in Qty up to last week |
Work planned during the week |
Actual work done during the week |
Cumulative delay in Qty up to this week |
Work Planned for next week |
No of days remaing for completion as per the weekly plan |
Remarks |
1 |
PILE CHERUVATHOOR SIDE |
27 |
27 |
Completed |
|
|
2 |
PILE PADANNA SIDE |
24 |
24 |
Completed |
|
Piling works completed. |
3 |
PILE CAP CHERUVATHOOR SIDE |
9 |
9 |
Completed |
|
|
4 |
PILE CAP PADANNA SIDE |
8 |
8 |
Completed |
|
|
5 |
PIER CHERUVATHOOR SIDE |
9 |
9 |
Completed |
|
|
6 |
PIER PADANNA SIDE |
8 |
8 |
Completed |
|
|
7 |
PIER CAP CHERUVATHOOR SIDE |
9 |
9 |
Completed |
|
|
8 |
PIER CAP PADANNA SIDE |
8 |
8 |
Completed |
|
|
9 |
RE/R WALL CHERUVATHOOR SIDE |
100% |
60% |
40% |
20% |
20.00% |
5.00% |
30.00% |
20.00% |
|
RE Panel third layer in progress,RC Wall 90% complete. |
10 |
RE/R WALL PADANNA SIDE |
100% |
0 |
100% |
5% |
5.00% |
0.00% |
10.00% |
5.00% |
|
|
11 |
BEAM/SLAB CHERUVATHOOR SIDE |
9 |
5 |
4 |
0 |
0.5 |
0 |
0.5 |
1 |
|
shuttering 80% complete for P12-P11 girder |
12 |
BEAM/SLAB PADANNA SIDE |
8 |
5.5 |
2.5 |
0 |
0.5 |
0.5 |
0 |
0 |
|
P4-P5 slab complete,AP1-P1 location bsnl cable shifting in progress. |
13 |
EXPANSION JOINT CHERUVATHUR SIDE |
9 |
0 |
9 |
0 |
3 |
2 |
1 |
1 |
|
P15,P14 locations |
14 |
EXPANSION JOINT PADANNA SIDE |
8 |
0 |
8 |
0 |
0 |
0 |
0 |
0 |
|
|
15 |
KERB CHERUVATHOOR SIDE |
100% |
0 |
100% |
0 |
12.50% |
0.00% |
12.50% |
12.50% |
|
|
16 |
KERB PADANNA SIDE |
100% |
0 |
100% |
0 |
0.00% |
0.00% |
0.00% |
0.00% |
|
|
17 |
HANDRAIL CHERUVATHUR SIDE |
100% |
0 |
100% |
0 |
0.00% |
0.00% |
0.00% |
0.00% |
|
Handrail horizontal casting IP |
18 |
HANDRAIL PADANNA SIDE |
100% |
0 |
100% |
0 |
0.00% |
0.00% |
0.00% |
0.00% |
|
|
17 |
BC/PAINTING |
100% |
0 |
100% |
0 |
0.00% |
0.00% |
0.00% |
0.00% |
|
|
16 |
Deck Slab |
|
|
|
|
|
|
|
|
|
|
17 |
Utility shifting |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
Availbility of Men |
|
|
|
|
|
|
|
|
|
|
|
Date |
28-04-2012 |
29-04-2012 |
30-04-2012 |
01-05-2012 |
02-05-2012 |
03-05-2012 |
04-05-2012 |
|
|
|
|
No of labours |
74 |
64 |
64 |
46 |
57 |
68 |
67 |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
Material Stocking Status |
Required |
Available |
Remarks |
|
|
|
|
|
|
|
|
Coarse Aggreagate (m3) |
available |
|
|
|
|
|
|
|
|
|
Fine Aggreagate(m3) |
available |
|
|
|
|
|
|
|
|
|
Cement(bag) |
500 |
800 |
|
|
|
|
|
|
|
|
|
Steel(MT) |
8 |
15 |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
Utility shifting |
|
|
|
|
|
|
|
|
|
|
|
Utilities to be shifted |
Status |
Remarks |
|
|
|
|
|
|
|
|
|
BSNL |
work to be started immediately at padanna side approach portion.Work in progress at AP1-P1 deck slab location. |
|
|
|
|
|
|
|
KSEB |
in progress |
electric post infront of unity hospital need to be shifted urgently. |
|
|
|
|
|
|
|
KWA |
currently can be managed at site |
|
|
|
|
|
|
|
|
|
|
Others |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|