   Weekly progress report as on 04.05.2012
    

PROGRESS REPORT (upto May 4th 2012)

RAILWAY PORTION

Total scope: 4 Locations

 

 

LOCATIONS:P1,P7  ,P8,P2

P1,P7 –N.H side

P8,P2-Pulikkakadavu side.

Total Piles: 18

 

No of PILES IN EACH LOCATION

P1 location: 4

P7 location:5

P8 location:5

P2 location:4

 

WORK COMPLETED IN EACH LOCATION OF RAILWAY PORTION

P1 location:Piling completed (4 piles),pile cap,trestle column,trestle beam.

P7 location:5 pile concreting completed,pile cap,trestle column,trestle beam

 

P8 location:Piling completed(5 piles),pile cap,Trestle column,trestle beam

P2 location:Piling completed(4 piles),pile cap,trestle column,trestle beam.

 

Approach portion at N.H side completed 40%

 

WORK COMPLETED AT PULIKKAKADAVU SIDE

All deck slab concreting completed at pulikkakadavu side.

Works completed upto the roadworks,miscellaneous works, in the approach portion at pulikkakadavu side.

WORKS BALANCE

P1-P7 superstructure (RCC structure)

P7-P8 superstructure( CENTRAL SPAN)

P8-P2 superstructure (RCC structure)

 

 

Awaiting the sanction from the railways for the superstructure drawing.

WORK COMPLETED THIS WEEK

1.RE block laying in progress along with backfilling of soil in the abutment portion at NH side.

2.Pedestal reinforcement of the span P2-P8 in progress.

3.Staging work for P2-P8 Span completed.

 

 

 

 

 

LABOUR REPORT

DATE

NO: OF LABOURS

28-04-2012

9

30-4-2012

9

1-5-2012

3

2-5-2012

10

3-5-2012

9

4-5-2012

8

 

 

 

 

 

 
Back
 
    
RE WALL WORK IN PROGRESS

    
    
PEDESTAL REINFORCEMENT WORK IN PROGRESS AT P2

    
    
NETTING WORK AT RE WALL PORTION AT N.H PORTION.

    
    
NETTING WORK AT RE WALL PORTION AT N.H PORTION.

    
 
 
 

 

 

 

 

 

 

 