   11.09.2010
    

ROB at Payyannur

Description    Completed/ Progress Remarks
GAD Submitted Comments Released for Revision
Centre line marking Completed     
Drawings for Pile & Pile cap (Group 1) and Super Structure Approved  
Drawings of Super Structure Approved  
Earth filling for leveling work In progress    Slow progress due to heavy rains
Piling work Not Started  
 